3015.165—Rights to require transfer of equipment.
(a) USDA right.
The awarding agency shall have the right to require the transfer of equipment (including title) for items of equipment having a unit cost of $1,000 or more to the Federal government or to an eligible non-Federal party named by the awarding agency. Normally, USDA agencies will only exercise this right if the project or program for which the equipment was acquired is transferred from one recipient to another. The following conditions shall govern this right:
(2)
In order for the awarding agency to exercise the right, disposition instructions must be issued no later than 120 days after the end of USDA grant support for the project or program for which the equipment was acquired. Furthermore:
(i)
If the equipment is eligible for the exemptions in § 3015.164 and ceases to be needed for the project or program for which it was acquired while the project or program is still being performed by the recipient, the disposition instructions must have been received by the recipient while the equipment was still needed for that project or program.
(ii)
If the equipment is not eligible for those exemptions, disposition instructions must have been received by the recipient before other permissible disposition of the equipment took place in accordance with § 3015.168.
(3)
If the right is exercised, the recipient shall be entitled to be paid any reasonable, resulting shipping or storage costs incurred, plus an amount computed by multiplying the market value of the equipment by the non-Federal share of the equipment.
(b) Right of parties awarding subgrants.
A recipient may reserve for itself, when awarding a subgrant, rights similar to those found in paragraph (a) of this section which covers items of equipment having a unit acquisition cost of $1,000 or more which are acquired under that subgrant. Without the approval of the awarding agency, the right may be exercised only if the project or program for which the equipment was acquired is transferred to another subrecipient and only for the purpose of transferring the equipment to the new subrecipient for continued use in the project or program.
(c) Equipment lists.
If at any time an awarding agency is considering exercising its right to require transfer of equipment, it may require the recipient to furnish it with a list of all items of equipment that are subject to the right. As such, the awarding agency will decide which items, if any, should be transferred.