633.29—PMP waivers.
A waiver will be considered upon initiation by the grantee or by the agency itself. The Administrator may, on a case-by-case basis, waive:
(a)
Any of the PMP elements in § 633.25 of this part if the Administrator determines the element is not necessary for a particular plan; or
(b)
The requirement of having a new project management plan submitted for a major capital project if a recipient seeks to manage the major capital project under a previously-approved project management plan.