232.505—Pre-revenue service acceptance testing plan.
(a) General; submission of plan.
Except as provided in paragraph (f) of this section, before using a new brake system technology for the first time on its system the operating railroad or railroads shall submit a pre-revenue service acceptance testing plan containing the information required by paragraph (e) of this section and obtain the approval of the FRA Associate Administrator for Safety, under the procedures specified in § 232.17.
(b) Compliance with plan.
After receiving FRA approval of the pre-revenue service testing plan and before introducing the new brake system technology into revenue service, the operating railroad or railroads shall:
(1)
Adopt and comply with such FRA-approved plan, including fully executing the tests required by the plan;
(2)
Report to the FRA Associate Administrator for Safety the results of the pre-revenue service acceptance tests;
(3)
Correct any safety deficiencies identified by FRA in the design of the equipment or in the inspection, testing, and maintenance procedures or, if safety deficiencies cannot be corrected by design or procedural changes, agree to comply with any operational limitations that may be imposed by the Associate Administrator for Safety on the revenue service operation of the equipment; and
(c) Compliance with limitations.
The operating railroad shall comply with each operational limitation, if any, imposed by the Associate Administrator for Safety.
(d) Availability of plan.
The plan shall be made available to FRA for inspection and copying upon request.
(1)
An identification of each waiver, if any, of FRA or other Federal safety regulations required for the tests or for revenue service operation of the equipment.
(2)
A clear statement of the test objectives. One of the principal test objectives shall be to demonstrate that the equipment meets the safety design and performance requirements specified in this part when operated in the environment in which it is to be used.
(10)
A description of the criteria to be used to measure or determine the success or failure of the tests. If acceptance is to be based on extrapolation of less than full level testing results, the analysis to be done to justify the validity of the extrapolation shall be described.
(12)
A written set of standard operating procedures to be used to ensure that the testing is done safely.
(13)
Quality control procedures to ensure that the inspection, testing, and maintenance procedures are followed.
(f) Exception.
For brake system technologies that have previously been used in revenue service in the United States, the railroad shall test the equipment on its system, prior to placing it in revenue service, to ensure the compatibility of the equipment with the operating system (track, signals, etc.) of the railroad. A description of such testing shall be retained by the railroad and made available to FRA for inspection and copying upon request.