1155.13—Board determination with respect to a Governor's petition.

Day 0—Petition filed.
Day 20—Due date for reply.
Day 30—Due date for response to reply.
(b) The Board shall accept the Governor's complete petition on a finding that the facility qualifies as a solid waste rail transfer facility pursuant to the definition in 49 U.S.C. 10908(e)(1)(H) and 49 CFR 1155.2 both on the filing date of the petition and on October 16, 2008. In the decision accepting the Governor's petition, the Board shall require that the rail carrier that owns or operates the facility file a land-use-exemption-permit application within 120 days of the service date of the decision.