154.650—Cargo tank and process pressure vessel welding.
(1)
Each welded joint of the shells must be a full penetration butt weld, except dome to shell connections may have full penetration tee welds.
(d)
Each welded joint in an independent tank type C or in a process pressure vessel must meet Part 54 of this chapter, except that any backing rings must be removed unless specially approved by the Commandant (CG-522).
(e)
Each welded joint in a membrane tank must meet the quality assurance measures, weld procedure qualification, design details, materials, construction, inspection, and production testing of components developed during the prototype testing program that are specially approved by the Commandant (CG-522) under this part.
[CGD 74-289, 44 FR 26009, May 3, 1979, as amended by CGD 82-063b, 48 FR 4782, Feb. 3, 1983]