10005.16—Plan content.
(1)
A summary of basic information from the planning rule, including project evaluation procedures and plan amendment procedures,
(3)
A list, and description, of the projects selected for implementation during the term of the plan—with particular emphasis on projects to be implemented early in the planning cycle,
(4)
A description of the relationship between the projects to be included in the plan and the Commission's mitigation obligations,
(1)
A discussion of the relationship of the plan to other activities affecting fish, wildlife, and recreation resources within the State of Utah, and/or
(2)
Discussions of, or information on, other topics that the Commission determines to be relevant. For example, the Commission may wish to identify mitigation and/or conservation measures that the Commission may wish to consider in later years of the five-year plan or in subsequent five-year plans.