96.21—Submission of NO X Budget permit applications.
(a) Duty to apply.
The NOX authorized account representative of any NOX Budget source required to have a federally enforceable permit shall submit to the permitting authority a complete NOX Budget permit application under § 96.22 by the applicable deadline in paragraph (b) of this section.
(i)
For any source, with one or more NOX Budget units under § 96.4 that commence operation before January 1, 2000, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 covering such NOX Budget units to the permitting authority at least 18 months (or such lesser time provided under the permitting authority's title V operating permits regulations for final action on a permit application) before May 1, 2003.
(ii)
For any source, with any NOX Budget unit under § 96.4 that commences operation on or after January 1, 2000, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 covering such NOX Budget unit to the permitting authority at least 18 months (or such lesser time provided under the permitting authority's title V operating permits regulations for final action on a permit application) before the later of May 1, 2003 or the date on which the NOX Budget unit commences operation.
(i)
For any source, with one or more NOX Budget units under § 96.4 that commence operation before January 1, 2000, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 covering such NOX Budget units to the permitting authority at least 18 months (or such lesser time provided under the permitting authority's non-title V permits regulations for final action on a permit application) before May 1, 2003.
(ii)
For any source, with any NOX Budget unit under § 96.4 that commences operation on or after January 1, 2000, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 covering such NOX Budget unit to the permitting authority at least 18 months (or such lesser time provided under the permitting authority's non-title V permits regulations for final action on a permit application) before the later of May 1, 2003 or the date on which the NOX Budget unit commences operation.
(c) Duty to reapply.
(1)
For a NOX Budget source required to have a title V operating permit, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 for the NOX Budget source covering the NOX Budget units at the source in accordance with the permitting authority's title V operating permits regulations addressing operating permit renewal.
(2)
For a NOX Budget source required to have a non-title V permit, the NOX authorized account representative shall submit a complete NOX Budget permit application under § 96.22 for the NOX Budget source covering the NOX Budget units at the source in accordance with the permitting authority's non-title V permits regulations addressing permit renewal.