93.114—Criteria and procedures: Currently conforming transportation plan and TIP.
         There must be a currently conforming transportation plan and currently conforming TIP at the time of project approval, or a project must meet the requirements in  § 93.104(f) during the 12-month lapse grace period.
    
    
        
        (a) 
         Only one conforming transportation plan or TIP may exist in an area at any time; conformity determinations of a previous transportation plan or TIP expire once the current plan or TIP is found to conform by DOT. The conformity determination on a transportation plan or TIP will also lapse if conformity is not determined according to the frequency requirements specified in  § 93.104.
    
    
        
        (b) 
         This criterion is not required to be satisfied at the time of project approval for a TCM specifically included in the applicable implementation plan, provided that all other relevant criteria of this subpart are satisfied.