76.14—Monitoring, recordkeeping, and reporting.
(a)
A petition for an alternative emission limitation demonstration period under § 76.10(d) shall include the following information:
(i)
Documentation that the owner or operator solicited bids for a NOX emission control system designed for application to the specific boiler and designed to achieve the applicable emission limitation in § 76.5, 76.6, or 76.7 on an annual average basis. This documentation must include a copy of all bid specifications.
(ii)
A copy of the performance guarantee submitted by the vendor of the installed NOX emission control system to the owner or operator showing that such system was designed to meet the applicable emission limitation in § 76.5, 76.6, or 76.7 on an annual average basis.
(iii)
Documentation describing the operational and combustion conditions that are the basis of the performance guarantee.
(iv)
Certification by the primary vendor of the NOX emission control system that such equipment and associated auxiliary equipment was properly installed according to the modifications and procedures specified by the vendor.
(v)
Certification by the designated representative that the owner(s) or operator installed technology that meets the requirements of § 76.10(a)(2).
(i)
The operating conditions of the NOX emission control system including load range, O2 range, coal volatile matter range, and, for tangentially fired boilers, distribution of combustion air within the NOX emission control system;
(ii)
Certification by the designated representative that the owner(s) or operator have achieved and are following the operating conditions, boiler modifications, and upgrades that formed the basis for the system design and performance guarantee;
(iii)
Any planned equipment modifications and upgrades for the purpose of achieving the maximum NOX reduction performance of the NOX emission control system that were not included in the design specifications and performance guarantee, but that were achieved prior to submission of this application and are being followed;
(iv)
A list of any modifications or replacements of equipment that are to be done prior to the completion of the demonstration period for the purpose of reducing emissions of NOX; and
(v)
The parametric testing that will be conducted to determine the reason or reasons for the failure of the unit to achieve the applicable emission limitation and to verify the proper operation of the installed NOX emission control system during the demonstration period. The tests shall include tests in § 76.15, which may be modified as follows:
(A)
The owner or operator of the unit may add tests to those listed in § 76.15, if such additions provide data relevant to the failure of the installed NOX emission control system to meet the applicable emissions limitation in § 76.5, 76.6, or 76.7; or
(B)
The owner or operator of the unit may remove tests listed in § 76.15 that are shown, to the satisfaction of the permitting authority, not to be relevant to NOX emissions from the affected unit; and
(C)
In the event the performance guarantee or the NOX emission control system specifications require additional tests not listed in § 76.15, or specify operating conditions not verified by tests listed in § 76.15, the owner or operator of the unit shall include such additional tests.
(iii)
Hourly NOX emission rate (in lb/mmBtu), calculated in accordance with part 75 of this chapter ;
(iv)
Total heat input (in mmBtu) for the unit for each hour of operation, calculated in accordance with the requirements of part 75 of this chapter; and
(b)
A petition for an alternative emission limitation shall include the following information in accordance with § 76.10(e)(6).
(1)
Total heat input (in mmBtu) for the unit for each hour of operation, calculated in accordance with the requirements of part 75 of this chapter ;
(2)
Hourly NOX emission rate (in lb/mmBtu), calculated in accordance with the requirements of part 75 of this chapter; and
(c)
Reporting of the costs of low NO
X
burner technology applied to Group 1, Phase I boilers. (1) Except as provided in paragraph (c)(2) of this section, the designated representative of a Phase I unit with a Group 1 boiler that has installed or is installing any form of low NOX burner technology shall submit to the Administrator a report containing the capital cost, operating cost, and baseline and post-retrofit emission data specified in appendix B to this part. If any of the required equipment, cost, and schedule information are not available (e.g., the retrofit project is still underway), the designated representative shall include in the report detailed cost estimates and other projected or estimated data in lieu of the information that is not available.
(2)
The report under paragraph (c)(1) of this section is not required with regard to the following types of Group 1, Phase I units:
(ii)
Units employing modifications to boiler operating parameters (e.g., burners out of service or fuel switching) without low NOX burners or other emission reduction equipment for reducing NOX emissions;
(iii)
Units with wall-fired boilers employing only overfire air and units with tangentially fired boilers employing only separated overfire air; or