52.2273—Approval status.

(a) With the exceptions set forth in this subpart, the Administrator approves Texas' plan for the attainment and maintenance of the national standards under section 110 of the Clean Air Act. Furthermore, the Administrator finds that the plan satisfies all requirements of Part D, Title 1, of the Clean Air Act as amended in 1977, except as noted below.
(b) EPA is disapproving the Texas SIP revision submittals as follows:
(1) The following definitions in 30 TAC 116.10—General Definitions:
(i) Definition of “actual emissions” in 30 TAC 116.10(1), submitted March 13, 1996 and repealed and re-adopted June 17, 1998 and submitted July 22, 1998;
(ii) Definition of “allowable emissions” in 30 TAC 116.10(2), submitted March 13, 1996; repealed and re-adopted June 17, 1998 and submitted July 22, 1998; and submitted September 11, 2000;
(iii) Portion of the definition of “modification of existing facility” in 30 TAC 116.10(11)(E), submitted March 13, 1996; repealed and re-adopted June 17, 1998 and submitted July 22, 1998; and submitted September 4, 2002; and
(iv) Definition of “qualified facility” in 30 TAC 116.10(16), submitted March 13, 1996; repealed and re-adopted June 17, 1998 and submitted July 22, 1998; and submitted September 4, 2002;
(2) 30 TAC 116.116(e)—Changes at Qualified Facilities—submitted March 13, 1996 and repealed and re-adopted June 17, 1998 and submitted July 22, 1998;
(3) 30 TAC 116.117—Documentation and Notification of Changes to Qualified Facilities—submitted March 13, 1996 and repealed and re-adopted June 17, 1998 and submitted July 22, 1998;
(4) 30 TAC 116.118—Pre-Change Qualification—submitted March 13, 1996 and repealed and re-adopted June 17, 1998 and submitted July 22, 1998.
(c) EPA is disapproving the Texas SIP revision submittals under 30 TAC Chapter 116—Control of Air Pollution by Permits for New Construction or Modification as follows:
(1) The following provisions under 30 TAC Chapter 116, Subchapter A—Definitions:
(i) Portion of the definition of “modification of existing facility” in 30 TAC 116.10(11)(F), submitted March 13, 1996; repealed and readopted June 17, 1998 and submitted July 22, 1998; adopted August 9, 2000 and submitted September 11, 2000; and revised August 21, 2002 and submitted September 4, 2002;
(ii) 30 TAC 116.13—Flexible Permit Definitions, adopted November 16, 1994 and submitted November 29, 1994; repealed and readopted June 17, 1998 and submitted July 22, 1998;
(2) The following provision in 30 TAC Chapter 116, Subchapter B—New Source Review Permits, Division 1—Permit Application: 30 TAC 116.110(a)(3)—Applicability, adopted November 16, 1994 and submitted November 29, 1994; repealed and readopted June 17, 1998 and submitted July 22, 1998;
(3) The following sections in 40 TAC Chapter 116, Subchapter G—Flexible Permits:
(i) 30 TAC 116.710—Applicability—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; and adopted August 9, 2000 and September 11, 2000;
(ii) 30 TAC 116.711—Flexible Permit Application—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; revised March 7, 2001 and submitted April 12, 2001; and revised August 21, 2002 and submitted September 4, 2002;
(iii) 30 TAC 116.714—Application Review Schedule—adopted November 16, 1994 and submitted November 29, 1994, and revised June 17, 1998 and submitted July 22, 1998;
(iv) 30 TAC 116.715—General and Special Conditions—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; adopted August 9, 2000 and submitted September 11, 2000; revised March 7, 2001 and submitted April 12, 2001; revised August 21, 2002 and submitted September 4, 2002; and revised August 20, 2003 and submitted September 25, 2003;
(v) 30 TAC 116.716—Emission Caps and Individual Limitations—adopted November 16, 1994 and submitted November 29, 1994;
(vi) 30 TAC 116.717—Implementation Schedule for Additional Controls—adopted November 16, 1994 and submitted November 29, 1994;
(vii) 30 TAC 116.718—Significant Emission Increase—adopted November 16, 1994 and submitted November 29, 1994;
(viii) 30 TAC 116.720—Limitation on Physical and Operational Changes—adopted November 16, 1994 and submitted November 29, 1994;
(ix) 30 TAC 116.721—Amendments and Alterations—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; and revision adopted August 9, 2000 and submitted September 11, 2000;
(x) 30 TAC 116.722—Distance Limitations—adopted November 16, 1994 and submitted November 29, 1994; and revision adopted August 9, 2000 and submitted September 11, 2000;
(xi) 30 TAC 116.730—Compliance History—adopted November 16, 1994 and submitted November 29, 1994; and revised June 17, 1998 and submitted July 22, 1998;
(xii) 30 TAC 116.740—Public Notice and Comment—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; and revision adopted September 2, 1999 and submitted October 25, 1999;
(xiii) 30 TAC 116.750—Flexible Permit Fee—adopted November 16, 1994 and submitted November 29, 1994; revised June 17, 1998 and submitted July 22, 1998; adopted August 9, 2000 and submitted September 11, 2000; and revision adopted September 25, 2002 and submitted October 4, 2002;
(xiv) 30 TAC 116.760—Flexible Permit Renewal—adopted November 16, 1994 and submitted November 29, 1994.
(d) EPA is disapproving the Texas SIP revision submittals under 30 TAC Chapter 116—Control of Air Pollution by Permits for New Construction and Modification as follows:
(1) The following provisions in 30 TAC Chapter 116, Subchapter A—Definitions:
(i) 30 TAC 116.10—General Definitions—the definition of “BACT” in 30 TAC 116.10(3), adopted February 14, 1996, and submitted March 13, 1996; and repealed and readopted June 17, 1998, and submitted July 22, 1998;
(ii) The revisions to 30 TAC 116.12—Nonattainment Review Definition, adopted May 25, 2005, and submitted June 10, 2005;
(iii) The revisions to 30 TAC 116.12—Nonattainment and Prevention of Significant Deterioration Definitions, adopted January 11, 2006, and submitted February 1, 2006 (which renamed the section title);
(2) The following section in 30 TAC Chapter 116, Subchapter B—New Source Review Permits, Division 1—Permit Application: 30 TAC 116.121—Actual to Projected Actual Test for Emission Increase, adopted January 11, 2006, and submitted February 1, 2006;
(3) The following sections in 30 TAC Chapter 116, Subchapter B—New Source Review Permits, Division 5—Nonattainment Review:
(i) Revisions to 30 TAC 116.150—New Major Source or Modification in Ozone Nonattainment Area—revisions adopted May 25, 2005, and submitted June 10, 2005; and revisions adopted January 11, 2006, and submitted February 1, 2006;
(ii) Revisions to 30 TAC 116.151—New Major Source or Modification in Nonattainment Areas Other Than Ozone—revisions adopted January 11, 2006, and submitted February 1, 2006;
(4) The following sections in 30 TAC Chapter 116, Subchapter C—Plant-Wide Applicability Limits, Division 1—Plant-Wide Applicability Limits:
(i) 30 TAC 116.180—Applicability—adopted January 11, 2006, and submitted February 1, 2006;
(ii) 30 TAC 116.182—Plant-Wide Applicability Limit Permit Application—adopted January 11, 2006, and submitted February 1, 2006;
(iii) 30 TAC 116.184—Application Review Schedule—adopted January 11, 2006, and submitted February 1, 2006;
(iv) 30 TAC 116.186—General and Special Conditions—adopted January 11, 2006, and submitted February 1, 2006;
(v) 30 TAC 116.188—Plant-Wide Applicability Limit—adopted January 11, 2006, and submitted February 1, 2006;
(vi) 30 TAC 116.190—Federal Nonattainment and Prevention of Significant Deterioration Review—adopted January 11, 2006, and submitted February 1, 2006;
(vii) 30 TAC 116.192—Amendments and Alterations—adopted January 11, 2006, and submitted February 1, 2006;
(viii) 30 TAC 116.194—Public Notice and Comment—adopted January 11, 2006, and submitted February 1, 2006;
(ix) 30 TAC 116.196—Renewal of a Plant-Wide Applicability Limit Permit—adopted January 11, 2006, and submitted February 1, 2006;
(x) 30 TAC 116.198—Expiration and Voidance—adopted January 11, 2006, and submitted February 1, 2006;
(5) The following sections in 30 TAC Chapter 116, Subchapter F—Standard Permits:
(i) Revisions to 30 TAC 116.610—Applicability—paragraphs (a)(1) through (a)(5) and (b)—revisions adopted January 11, 2006, and submitted February 1, 2006;
(ii) 30 TAC 116.617—State Pollution Control Project Standard Permit—adopted January 11, 2006, and submitted February 1, 2006;
(e) EPA is disapproving the Texas SIP revision submittals under 30 TAC Chapter 101—General Air Quality Rules as follows:
(1) Subchapter F—Emissions Events and Scheduled Maintenance, Startup, and Shutdown Activities, Division 1— Section 101.222 (Demonstrations): Sections 101.222(h), 101.222(i), and 101.222(j), adopted December 14, 2005, and submitted January 23, 2006.
(f) EPA is disapproving the Texas SIP revision submittals under 30 TAC Chapter 116—Control of Air Pollution by Permits for New Construction or Modification as follows:
(1) Subchapter I—Electric Generating Facility Permits— Section 116.911(a)(2) (Electric Generating Facility Permit), adopted December 16, 1999, and submitted January 3, 2000.

Code of Federal Regulations

[45 FR 19244, Mar. 25, 1980, as amended at 49 FR 32190, Aug. 13, 1984; 61 FR 16062, Apr. 11, 1996; 75 FR 19493, Apr. 14, 2010; 75 FR 41335, July 15, 2010; 75 FR 56452, Sept. 15, 2010; 75 FR 69002, Nov. 10, 2010; 76 FR 1532, Jan. 11, 2011]