21.8—Remedies.

(a) If GAO determines that a solicitation, cancellation of a solicitation, termination of a contract, proposed award, or award does not comply with statute or regulation, it shall recommend that the agency implement any combination of the following remedies:
(1) Refrain from exercising options under the contract;
(2) Terminate the contract;
(3) Recompete the contract;
(4) Issue a new solicitation;
(5) Award a contract consistent with statute and regulation; or
(6) Such other recommendation(s) as GAO determines necessary to promote compliance.
(b) In determining the appropriate recommendation(s), GAO shall, except as specified in paragraph (c) of this section, consider all circumstances surrounding the procurement or proposed procurement including the seriousness of the procurement deficiency, the degree of prejudice to other parties or to the integrity of the competitive procurement system, the good faith of the parties, the extent of performance, the cost to the government, the urgency of the procurement, and the impact of the recommendation(s) on the agency's mission.
(c) If the head of the procuring activity determines that performance of the contract notwithstanding a pending protest is in the government's best interest, GAO shall make its recommendation(s) under paragraph (a) of this section without regard to any cost or disruption from terminating, recompeting, or reawarding the contract.
(d) If GAO determines that a solicitation, proposed award, or award does not comply with statute or regulation, it may recommend that the agency pay the protester the costs of:
(1) Filing and pursuing the protest, including attorneys' fees and consultant and expert witness fees; and
(2) Bid and proposal preparation.
(e) If the agency decides to take corrective action in response to a protest, GAO may recommend that the agency pay the protester the reasonable costs of filing and pursuing the protest, including attorneys' fees and consultant and expert witness fees. The protester shall file any request that GAO recommend that costs be paid within 15 days of the date on which the protester learned (or should have learned, if that is earlier) that GAO had closed the protest based on the agency's decision to take corrective action. The protester shall furnish a copy of its request to the agency, which may file a response within 15 days after receipt of the request, with a copy furnished to the protester.
(f) (1) If GAO recommends that the agency pay the protester the costs of filing and pursuing the protest and/or of bid or proposal preparation, the protester and the agency shall attempt to reach agreement on the amount of costs. The protester shall file its claim for costs, detailing and certifying the time expended and costs incurred, with the agency within 60 days after receipt of GAO's recommendation that the agency pay the protester its costs. Failure to file the claim within that time may result in forfeiture of the protester's right to recover its costs.
(2) The agency shall issue a decision on the claim for costs as soon as practicable after the claim is filed. If the protester and the agency cannot reach agreement within a reasonable time, GAO may, upon request of the protester, recommend the amount of costs the agency should pay in accordance with 31 U.S.C. 3554(c). In such cases, GAO may also recommend that the agency pay the protester the costs of pursuing the claim for costs before GAO.
(3) The agency shall notify GAO within 60 days after GAO recommends the amount of costs the agency should pay the protester of the action taken by the agency in response to the recommendation.

Code of Federal Regulations

[61 FR 39042, July 26, 1996, as amended at 67 FR 79836, Dec. 31, 2002]