61.62—Program changes.
(a)
Except as provided in paragraphs (b) through (d) of this section, a recipient may not make any significant changes to a project for which a grant has been awarded without prior VA approval. Significant changes include, but are not limited to, a change in the recipient, a change in the project site (including relocating, adding an annex, a branch, or other expansion), additions or deletions of activities, shifts of funds from one approved type of activity to another, and a change in the category of participants to be served.
(b)
Recipients of grants exceeding $100,000 for nonconstruction projects must receive prior VA approval for cumulative transfers among direct cost categories which exceed or are expected to exceed 10 percent of the current total approved budget.
(c)
Recipients of grants for projects involving both construction and nonconstruction who are State or local governments must receive prior VA approval for any budget revision which would transfer funds between nonconstruction and construction categories.
(d)
Approval for changes is contingent upon the application ranking remaining high enough after the approved change to have been competitively selected for funding in the year the application was selected.