379.54—What are the reporting requirements for the compliance indicators?

(a) To receive continuation funding for the third or any subsequent year of a PWI grant, each grantee must submit to the Secretary data for the most recent complete budget period no later than 60 days after the end of that budget period, unless the Secretary authorizes a later submission date. The Secretary uses this data to determine if the grantee has met the program compliance indicators in this subpart F.
(b) A grantee may receive its second year of funding (or the first continuation award) under this program before data from the first complete budget period is available. However, to allow the Secretary to determine whether the grantee is eligible for the third year of funding (or the second continuation award), the grantee must submit data from the first budget period in accordance with paragraph (a) of this section.
(c) If the data for the most recent complete budget period provided under paragraph (a) or (b) of this section show that a grantee has failed to achieve the minimum performance levels, as required by § 379.50(b), the grantee may, at its option, submit data from the first 6 months of the current budget period. The grantee must submit this data no later than 60 days after the end of that 6-month period, unless the Secretary authorizes a later submission date. The data must demonstrate that the grantee's project performance has improved sufficiently to meet the minimum performance levels required in § 379.50(b).
(Approved by the Office of Management and Budget under control number 1820-0631)

Code of Federal Regulations

(Authority: Section 611(f)(2) and 611(f)(4) of the Act; 29 U.S.C. 795(f)(2) and 795(f)(4) )