148.405—What are the procedures for notifying the Commandant (CG-5) of proposed site evaluation and pre-construction testing?
(a)
Any person who wants to conduct site evaluation and pre-construction testing at a potential site for a deepwater port must submit a written notice to the Commandant (CG-5) at least 30 days before the beginning of the evaluation or testing. The Commandant (CG-5) advises and coordinates with appropriate Federal agencies and the States concerning activities covered by this subpart.
(3)
Charts showing where the activities will be conducted and the locations of all offshore structures, including pipelines and cables, in or near the proposed area;
(7)
A preliminary report, based on existing data, of the historical and archeological significance of the area where the proposed activities are to take place. The report must include contacts made with any appropriate State liaison officers for historic preservation; and
(c)
For the following activities, the notice only needs the information required in paragraphs (b)(1), (b)(2), and (b)(5) of this section, as well as a general indication of the proposed location and purpose of the activities, including:
(2)
Bottom and sub-bottom acoustic profiling, within specified limits, without the use of explosives;
(3)
Sediment sampling of a limited nature using either core or grab samplers, and the specified diameter and depth to which the sampling would penetrate if geological profiles indicate no discontinuities that may have archeological significance;
(4)
Water and biotic sampling if the sampling does not adversely affect shellfish beds, marine mammals, or an endangered species, or if the sampling is permitted by another Federal agency;