148.125—What are the application fees?
(a)
The applicant must submit a nonrefundable application fee of $350,000 with each application for a license. If additional information is necessary to make an application complete, no additional application fee is required.
(b)
The costs incurred by the Federal Government in processing an application will be charged to the application fee until it is exhausted. If the fee is exhausted and the Federal Government incurs further processing costs, the applicant will be charged for the additional costs. The Commandant (CG-5) will periodically advise the applicant of the status of expenses incurred during the application process.
(c)
Additional costs attributable to processing a deepwater port license application and post-license activities, for example the engineering plan review or development of the final operations manual, are due when they are assessed, and must be paid by the applicant prior to commencing operation of the deepwater port.
(d)
Application fees and additional costs assessed under this section must be made payable to the United States Treasury, and submitted to the Commandant (CG-5).