651.5—Army policies.
(a)
NEPA establishes broad federal policies and goals for the protection of the environment and provides a flexible framework for balancing the need for environmental quality with other essential societal functions, including national defense. The Army is expected to manage those aspects of the environment affected by Army activities; comprehensively integrating environmental policy objectives into planning and decision-making. Meaningful integration of environmental considerations is accomplished by efficiently and effectively informing Army planners and decision makers. The Army will use the flexibility of NEPA to ensure implementation in the most cost-efficient and effective manner. The depth of analyses and length of documents will be proportionate to the nature and scope of the action, the complexity and level of anticipated effects on important environmental resources, and the capacity of Army decisions to influence those effects in a productive, meaningful way from the standpoint of environmental quality.
(b)
The Army will actively incorporate environmental considerations into informed decision-making, in a manner consistent with NEPA. Communication, cooperation, and, as appropriate, collaboration between government and extra-government entities is an integral part of the NEPA process. Army proponents, participants, reviewers, and approvers will balance environmental concerns with mission requirements, technical requirements, economic feasibility, and long-term sustainability of Army operations. While carrying out its mission, the Army will also encourage the wise stewardship of natural and cultural resources for future generations. Decision makers will be cognizant of the impacts of their decisions on cultural resources, soils, forests, rangelands, water and air quality, fish and wildlife, and other natural resources under their stewardship, and, as appropriate, in the context of regional ecosystems.
(c)
Environmental analyses will reflect appropriate consideration of non-statutory environmental issues identified by federal and DOD orders, directives, and policy guidance. Some examples are in § 651.14 (e). Potential issues will be discussed and critically evaluated during scoping and other public involvement processes.
(d)
The Army will continually take steps to ensure that the NEPA program is effective and efficient. Effectiveness of the program will be determined by the degree to which environmental considerations are included on a par with the military mission in project planning and decision-making. Efficiency will be promoted through the following:
(3)
Where appropriate, the use of programmatic analyses and tiering to ensure consideration at the appropriate decision levels, elimination of repetitive discussion, consideration of cumulative effects, and focus on issues that are important and appropriate for discussion at each level.
(4)
Use of the scoping and public involvement processes to limit the analysis of issues to those which are of interest to the public and/or important to the decision-making at hand.
(5)
Elimination of needless paperwork by focusing documents on the major environmental issues affecting those decisions.
(6)
Early integration of the NEPA process into all aspects of Army planning, so as to prevent disruption in the decision-making process; ensuring that NEPA personnel function as team members, supporting the Army planning process and sound Army decision-making. All NEPA analyses will be prepared by an interdisciplinary team.
(7)
Partnering or coordinating with agencies, organizations, and individuals whose specialized expertise will improve the NEPA process.
(8)
Oversight of the NEPA program to ensure continuous process improvement. NEPA requirements will be integrated into other environmental reporting requirements, such as the ISR.
(9)
Clear and concise communication of data, documentation, and information relevant to NEPA analysis and documentation.
(v)
Adaptive management of Army operations to stay on course with the strategic plan's specific resource goals.
(11)
Responsive staffing through HQDA and the Secretariat. To the extent possible, documents and transmittal packages will be acted upon within 30 calendar days of receipt by each office through which they are staffed. These actions will be approved and transmitted, if the subject material is adequate; or returned with comment in those cases where additional work is required. Cases where these policies are violated should be identified to ASA (I&E) for resolution.
(1)
Establish and maintain the capability (personnel and other resources) to ensure adherence to the policies and procedures specified by this part. This should include the use of the PPBES, EPR, and other established resourcing processes. This capability can be provided through the use of a given mechanism or mix of mechanisms (contracts, matrix support, and full-time permanent (FTP) staff), but sufficient FTP staff involvement is required to ensure:
(ii)
Sufficient institutional knowledge of the NEPA analysis to ensure that Army NEPA responsibilities (pre- and post-decision) are met. Every person preparing, implementing, supervising, and managing projects involving NEPA analysis must be familiar with the requirements of NEPA and the provisions of this part.
(2)
Ensure environmental responsibility and awareness among personnel to most effectively implement the spirit of NEPA. All personnel who are engaged in any activity or combination of activities that significantly affect the quality of the human environment will be aware of their NEPA responsibility. Only through alertness, foresight, notification through the chain of command, and training and education will NEPA goals be realized.
(f)
The worldwide, transboundary, and long-range character of environmental problems will be recognized, and, where consistent with national security requirements and U.S. foreign policy, appropriate support will be given to initiatives, resolutions, and programs designed to maximize international cooperation in protecting the quality of the world human and natural environment. Consideration of the environment for Army decisions involving activities outside the United States (see § 651.1(e)) will be accomplished pursuant to Executive Order 12114 (Environmental Effects Abroad of Major Federal Actions, 4 January 1979), host country final governing standards, DOD Directive (DODD) 6050.7 (Environmental Effects Abroad of Major DOD Actions), DOD Instructions (DODIs), and the requirements of this part. An environmental planning and evaluation process will be incorporated into Army actions that may substantially affect the global commons, environments of other nations, or any protected natural or ecological resources of global importance.
(g)
Army NEPA documentation must be periodically reviewed for adequacy and completeness in light of changes in project conditions.
(i)
The Army makes substantial changes in the proposed action that are relevant to environmental concerns; or
(ii)
There are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impact.
(2)
This review requires that the proponent merely initiate another “hard look” to ascertain the adequacy of the previous analyses and documentation in light of the conditions listed in paragraph (g)(1) of this section. If this review indicates no need for new or supplemental documentation, a REC can be produced in accordance with this part. Proponents are required to periodically review relevant existing NEPA analyses to ascertain the need for supplemental documentation and document this review in a REC format.
(h)
Contractors frequently prepare EISs and EAs. To obtain unbiased analyses, contractors must be selected in a manner avoiding any conflict of interest. Therefore, contractors will execute disclosure statements specifying that they have no financial or other interest in the outcome of the project. The contractor's efforts should be closely monitored throughout the contract to ensure an adequate assessment/statement and also avoid extensive, time-consuming, and costly analyses or revisions. Project proponents and NEPA program managers must be continuously informed and involved.
(i)
When appropriate, NEPA analyses will reflect review for operations security principles and procedures, described in AR 530-1 (Operations Security (OPSEC)), on the cover sheet or signature page.
(j)
Environmental analyses and associated investigations are advanced project planning, and will be funded from sources other than military construction (MILCON) funds. Operations and Maintenance Army (OMA), Operations and Maintenance, Army Reserve (OMAR), and Operations and Maintenance, Army National Guard (OMANG), RDT&E, or other operating funds are the proper sources of funds for such analysis and documentation. Alternative Environmental Compliance Achievement Program (non-ECAP) funds will be identified for NEPA documentation, monitoring, and other required studies as part of the MILCON approval process.
(k)
Costs of design and construction mitigation measures required as a direct result of MILCON projects will be paid from MILCON funds, which will be included in the cost estimate and description of work on DD Form 1391, Military Construction Project Data.
(l)
Response actions implemented in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) or the Resource Conservation and Recovery Act (RCRA) are not legally subject to NEPA and do not require separate NEPA analysis. As a matter of Army policy, CERCLA and RCRA analysis and documentation should incorporate the values of NEPA and:
(2)
Analyze all reasonable alternative remedies, evaluating the significance of impacts resulting from the alternatives examined; and
(3)
Consider public comments in the selection of the remedy. The decision maker shall ensure that issues involving substantive environmental impacts are addressed by an interdisciplinary team.
(m)
MATDEVs, scientists and technologists, and CBTDEVs are responsible for ensuring that their programs comply with NEPA as directed in this part.
(1)
Prior to assignment of a MATDEV to plan, execute, and manage a potential acquisition program, CBTDEVs will retain environmental analyses and data from requirements determination activities, and Science and Technology (S&T) organizations will develop and retain data for their technologies. These data will transition to the MATDEV upon assignment to plan, execute, and manage an acquisition program. These data (collected and produced), as well as the decisions made by the CBTDEVs, will serve as a foundation for the environment, safety, and health (ESH) evaluation of the program and the incorporation of program-specific NEPA requirements into the Acquisition Strategy. Programmatic ESH evaluation is considered during the development of the Acquisition Strategy as required by DOD 5000.2-R for all ACAT programs. Programmatic ESH evaluation is not a NEPA document. It is a planning, programming, and budgeting strategy into which the requirements of this part are integrated. Environmental analysis must be a continuous process throughout the materiel development program. During this continuous process, NEPA analysis and documentation may be required to support decision-making prior to any decision that will prejudice the ultimate decision or selection of alternatives ( 40 CFR 1506.1 ). In accordance with DOD 5000.2.R, the MATDEV is responsible for environmental analysis of acquisition life-cycle activities (including disposal). Planning to accomplish these responsibilities will be included in the appropriate section of the Acquisition Strategy.
(2)
MATDEVs are responsible for the documentation regarding general environmental effects of all aspects of the system (including operation, fielding, and disposal) and the specific effects for all activities for which he/she is the proponent.
(3)
MATDEVs will include, in their Acquisition Strategy, provisions for developing and supplementing their NEPA analyses and documentation, and provide data to support supplemental analyses, as required, throughout the life cycle of the system. The MATDEV will coordinate with ASA (AL&T) or MACOM proponent office, ACSIM, and ASA(I&E), identifying NEPA analyses and documentation needed to support milestone decisions. This requirement will be identified in the Acquisition Strategy and the status will be provided to the ACSIM representative prior to milestone review. The Acquisition Strategy will outline the system-specific plans for NEPA compliance, which will be reviewed and approved by the appropriate MDA and ACSIM. Compliance with this plan will be addressed at Milestone Reviews.
(n)
AR 700-142 requires that environmental requirements be met to support materiel fielding. During the development of the Materiel Fielding Plan (MFP), and Materiel Fielding Agreement (MFA), the MATDEV and the materiel receiving command will identify environmental information needed to support fielding decisions. The development of generic system environmental and NEPA analyses for the system under evaluation, including military construction requirements and new equipment training issues, will be the responsibility of the MATDEV. The development of site-specific environmental analyses and NEPA documentation (EAs/EISs), using generic system environmental analyses supplied by the MATDEV, will be the responsibility of the receiving Command.
(o)
Army proponents are encouraged to draw upon the special expertise available within the Office of the Surgeon General (OSG) (including the U.S. Army Center for Health Promotion and Preventive Medicine (USACHPPM)), and USACE District Environmental Staff to identify and evaluate environmental health impacts, and other agencies, such as USAEC, can be used to assess potential environmental impacts). In addition, other special expertise is available in the Army, DOD, other federal agencies, state and local agencies, tribes, and other organizations and individuals. Their participation and assistance is also encouraged.