516.66—Administrative and contractual actions.
(a)
The following remedial options should be considered in response to confirmed fraudulent activity:
(ii)
Nonaward of contract based upon a finding of contractor nonresponsibility. (If this appears to be a valid option, a DFARS 209.406-3 ( 48 CFR 209.406-3) report must be prepared where contractor nonresponsibility is based on lack of integrity).
(vi)
Withholding of payments to contractor. In the case of withholding pursuant to DFARS 2032.173, the Chief, PFD, is the Army Remedy Coordinating Official.
(b)
In cases which are pending review or action by DOJ, PFAs should coordinate with the DOJ attorney handling the case prior to initiating any contractual or administrative remedy. In the case of ongoing criminal investigations, this coordination will be accomplished through the appropriate DOD criminal investigation organization.