285.636—What notices must I provide MMS following approval of my COP?

You must notify MMS in writing of the following events, within the time periods provided:
(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.
(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.
(c) At least 7 days before commencing commercial operations.