285.601—When am I required to submit my plans to MMS?

Your plan submission requirements depend on whether your lease or grant was issued competitively or noncompetitively under subpart B or subpart C of this part.
(a) If your lease or grant is issued competitively, you must submit your SAP or your GAP within 6 months of issuance.
(b) If you request that a lease or grant be issued noncompetitively, you must submit your SAP or your GAP within 60 days after the Director issues a determination that there is no competitive interest.
(c) If you intend to continue your commercial lease with an operations term, you must submit a COP, or a FERC license application, at least 6 months before the end of your site assessment term.
(d) You may submit your COP or FERC license application with your SAP.
(1) You must provide sufficient data and information with your COP for MMS to complete the needed reviews and NEPA analysis; and
(2) The MMS may need to conduct additional reviews, including NEPA analysis, if significant new information becomes available after you complete your site assessment activities or you revise your COP. As a result of the additional reviews, we may require modification of your COP.