SUBPART Q—Decommissioning Activities (§250.1700 to §250.1754)
- 250.1700—What do the terms “decommissioning”, “obstructions”, and “facility” mean?
- 250.1701—Who must meet the decommissioning obligations in this subpart?
- 250.1702—When do I accrue decommissioning obligations?
- 250.1703—What are the general requirements for decommissioning?
- 250.1704—When must I submit decommissioning applications and reports?
- 250.1710—When must I permanently plug all wells on a lease?
- 250.1711—When will MMS order me to permanently plug a well?
- 250.1712—What information must I submit before I permanently plug a well or zone?
- 250.1713—Must I notify MMS before I begin well plugging operations?
- 250.1714—What must I accomplish with well plugs?
- 250.1715—How must I permanently plug a well?
- 250.1716—To what depth must I remove wellheads and casings?
- 250.1717—After I permanently plug a well, what information must I submit?
- 250.1721—If I temporarily abandon a well that I plan to re-enter, what must I do?
- 250.1722—If I install a subsea protective device, what requirements must I meet?
- 250.1723—What must I do when it is no longer necessary to maintain a well in temporary abandoned status?
- 250.1725—When do I have to remove platforms and other facilities?
- 250.1726—When must I submit an initial platform removal application and what must it include?
- 250.1727—What information must I include in my final application to remove a platform or other facility?
- 250.1728—To what depth must I remove a platform or other facility?
- 250.1729—After I remove a platform or other facility, what information must I submit?
- 250.1730—When might MMS approve partial structure removal or toppling in place?
- 250.1731—Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?
- 250.1740—How must I verify that the site of a permanently plugged well, removed platform, or other removed facility is clear of obstructions?
- 250.1741—If I drag a trawl across a site, what requirements must I meet?
- 250.1742—What other methods can I use to verify that a site is clear?
- 250.1743—How do I certify that a site is clear of obstructions?
- 250.1750—When may I decommission a pipeline in place?
- 250.1751—How do I decommission a pipeline in place?
- 250.1752—How do I remove a pipeline?
- 250.1753—After I decommission a pipeline, what information must I submit?
- 250.1754—When must I remove a pipeline decommissioned in place?