250.418—What additional information must I submit with my APD?

You must include the following with the APD:
(a) Rated capacities of the drilling rig and major drilling equipment, if not already on file with the appropriate District office;
(b) A drilling fluids program that includes the minimum quantities of drilling fluids and drilling fluid materials, including weight materials, to be kept at the site;
(c) A proposed directional plot if the well is to be directionally drilled;
(d) A Hydrogen Sulfide Contingency Plan (see § 250.490 ), if applicable, and not previously submitted;
(e) A welding plan (see §§ 250.109 to 250.113) if not previously submitted;
(f) In areas subject to subfreezing conditions, evidence that the drilling equipment, BOP systems and components, diverter systems, and other associated equipment and materials are suitable for operating under such conditions;
(g) A request for approval if you plan to wash out or displace some cement to facilitate casing removal upon well abandonment;
(h) Certification of your casing and cementing program as required in § 250.420(a)(6) ;
(i) Description of qualifications required by § 250.416(f) of any independent third party; and
(j) Such other information as the District Manager may require.

Code of Federal Regulations

[68 FR 8423, Feb. 20, 2003, as amended at 75 FR 63372, Oct. 14, 2010]