250.292—What must the DWOP contain?

You must include the following information in your DWOP:
(a) A description and schematic of the typical wellbore, casing, and completion;
(b) Structural design, fabrication, and installation information for each surface system, including host facilities;
(c) Design, fabrication, and installation information on the mooring systems for each surface system;
(d) Information on any active stationkeeping system(s) involving thrusters or other means of propulsion used with a surface system;
(e) Information concerning the drilling and completion systems;
(f) Design and fabrication information for each riser system (e.g., drilling, workover, production, and injection);
(g) Pipeline information;
(h) Information about the design, fabrication, and operation of an offtake system for transferring produced hydrocarbons to a transport vessel;
(i) Information about subsea wells and associated systems that constitute all or part of a single project development covered by the DWOP;
(j) Flow schematics and Safety Analysis Function Evaluation (SAFE) charts (API RP 14C, sub section 4.3c, incorporated by reference in § 250.198) of the production system from the Surface Controlled Subsurface Safety Valve (SCSSV) downstream to the first item of separation equipment;
(k) A description of the surface/subsea safety system and emergency support systems to include a table that depicts what valves will close, at what times, and for what events or reasons;
(l) A general description of the operating procedures, including a table summarizing the curtailment of production and offloading based on operational considerations;
(m) A description of the facility installation and commissioning procedure;
(n) A discussion of any new technology that affects hydrocarbon recovery systems;
(o) A list of any alternate compliance procedures or departures for which you anticipate requesting approval; and
(p) Payment of the service fee listed in § 250.125.

Code of Federal Regulations

[70 FR 51501, Aug. 30, 2005, as amended at 71 FR 40911, July 19, 2006]