250.208—If I conduct ancillary activities, what notices must I provide?
At least 30 calendar days before you conduct any G&G exploration or development G&G activity (see § 250.207(a) ), you must notify the Regional Supervisor in writing.
(2)
Provide the names of the vessel, its operator, and the person(s) in charge; the specific type(s) of operations you will conduct; and the instrumentation/techniques and vessel navigation system you will use;
(4)
Describe the potential adverse environmental effects of the proposed activity and any mitigation to eliminate or minimize these effects on the marine, coastal, and human environment.
(1)
Give written notice to MMS at least 15 calendar days before you conduct any other ancillary activity (see § 250.207(b) and (c)) in addition to those listed in § 250.207(a); and