250.1925—May BOEMRE direct me to conduct additional audits?
(a)
If BOEMRE identifies safety or non-compliance concerns based on the results of our inspections and evaluations, or as a result of an event, BOEMRE may direct you to have an independent third-party audit of your SEMS program, in addition to the regular audit required by § 250.1920, or BOEMRE may conduct an audit.
(ii)
The independent third-party audit must meet the requirements of § 250.1920 of this part and you must ensure that the independent third party submits the findings and conclusions of a BOEMRE-directed audit according to the requirements in § 250.1920 to BOEMRE within 30 days after the audit is completed.
(2)
If BOEMRE conducts the audit, BOEMRE will provide a report of the findings and conclusions within 30 days of the audit.
(c)
You must provide the BOEMRE a copy of your plan for addressing the deficiencies identified in the BOEMRE-directed audit within 30 days of completion of the audit as required in § 250.1920.