250.177—What additional requirements may the Regional Supervisor order for a suspension?
If MMS grants or directs a suspension under paragraph § 250.172(b), the Regional Supervisor may require you to:
(1)
The Regional Supervisor must approve or prescribe the scope for any site-specific study that you perform.
(2)
The study must evaluate the cause of the hazard, the potential damage, and the available mitigation measures.
(3)
You must pay for the study unless you request, and the Regional Supervisor agrees to arrange, payment by another party.
(6)
The Regional Supervisor will use the results of the study and any other information that becomes available:
(ii)
To determine any actions that you must take to mitigate or avoid any damage to the environment, life, or property.
(c)
Submit a revised Development and Production Plan (including any required mitigating measures); or
(d)
Submit a revised Development Operations Coordination Document according to 30 CFR part 250, subpart B.