1926.1432—Multiple-crane/derrick lifts—supplemental requirements.
(a) Plan development.
Before beginning a crane/derrick operation in which more than one crane/derrick will be supporting the load, the operation must be planned. The planning must meet the following requirements:
(3)
Where the qualified person determines that engineering expertise is needed for the planning, the employer must ensure that it is provided.
(1)
The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (lift director).
(2)
The lift director must review the plan in a meeting with all workers who will be involved with the operation.