84.80—Conditions for use of Lump Sum (fixed price or fixed amount) grants.

(a) Heads of awarding activities (HAAs) shall determine and publish the funding arrangement for award programs having a published program regulation or Notice of Funding Availability. For other awards, discretion may be provided to Grant Officers to determine the funding arrangement on a transaction basis. In such cases, Grant Officers shall document the basis for selection of the funding arrangement in the negotiation record. Appropriate consideration to fixed amount (lump sum) awards shall be made if one or more of the following conditions are present:
(1) The HUD funding amount is definitely less than the total actual cost of the project.
(2) The HUD funding amount does not exceed $100,000 or the small purchase threshold fixed at 41 U.S.C. 403 (11), whichever is greater.
(3) The project scope is very specific and adequate cost, historical, or unit pricing data is available to establish a fixed amount award with assurance that the recipient will realize no increment above actual cost.
(b) [Reserved]