572.225—Grant agreements; corrective and remedial actions.
(a) Terms and conditions.
After HUD approves an application for a planning grant or an implementation grant under this part, it will enter into a grant agreement with the recipient setting forth the amount of the grant and applicable terms and conditions. The grant agreement will be effective for purposes of this part and funds may be disbursed under the Cash and Management Information (C/MI) System, described in § 572.230, after the grant agreement has been executed by the authorized official of the recipient and HUD. Among other things, the grant agreement will provide that the recipient agrees:
(1)
To carry out the program in accordance with the provisions of this part, applicable law, the approved application, and all other applicable requirements; and
(2)
To comply with such other terms and conditions, including recordkeeping and reports, as HUD may establish for the purposes of administering, monitoring, and evaluating the program in an effective and efficient manner.
(b) Corrective and remedial actions.
(1)
HUD may withhold, withdraw, or recapture any portion of a grant, terminate the grant agreement, or take other appropriate action authorized under the grant agreement, if HUD determines that the recipient is failing to carry out the approved homeownership program in accordance with the terms of the approved application and this part, including failure to provide the contributions toward the match. Corrective or remedial actions that HUD may instruct the recipient to undertake include;
(i)
Preparing and following a schedule of actions or a management plan for properly completing the approved activities;
(ii)
Cancelling or revising the affected activities before expending grant funds for them, revising the grant budget as necessary, and substituting other eligible activities;
(iii)
Discontinuing draws under the C/MI System, and not incurring further costs for the affected activities;
(iv)
Reimbursing its HOPE 3 program account in the amount not used in accordance with this part and the grant agreement; and
(v)
In the case of implementation grants, making additional matching contributions in substitution for contributions not in compliance with this part and the grant agreement or submitting to HUD acceptable evidence that matching contributions sufficient to meet the total match required under this part and the grant agreement will be made, before additional draws are made.
(2)
If HUD determines that the recipient is not complying with the corrective or remedial actions agreed upon with the recipient, or as otherwise authorized in the grant agreement, HUD may implement the following additional corrective and remedial actions:
(ii)
Suspending the recipient's authority to make draws under the C/MI System for affected activities;
(iii)
Reducing (deobligating) the grant in the amount affected by the performance deficiency, including, in the case of implementation grants, failure to furnish matching contributions in the required amount;
(v)
Taking action against the recipient under 2 CFR part 2424 with respect to future HOPE 3, HUD, or federal grant awards; and
(3)
If the amount of grant funds that has been disbursed under the C/MI System exceeds the amount finally determined by HUD to be authorized (including any authorized deobligation), the recipient must repay such excess amount to HUD, and will have no right to reclaim or reuse such excess amount.
(c) Failure to complete and transfer a property to a homebuyer.
If a property assisted under this part or credited as match is not completed and transferred to homebuyers as required under this part, whether voluntarily by the recipient or otherwise, grant expenditures on the property are considered ineligible, and HOPE 3 funds for acquisition and rehabilitation must be repaid to the program account. Preliminary costs (such as architectural and engineering, inspection, and appraisal fees) expended before acquisition are considered general program expenses and need not be repaid.
(d) Failure to provide homeownership opportunities under an implementation grant.
Failure to provide at least 70 percent of the number of homeownership opportunities proposed in the application for an implementation grant within the timeframe specified in § 572.210(f) may result in remedial actions, as described in paragraph (b) of this section, being taken by HUD, including requiring repayment of all or part of the grant.