570.902—Review to determine if CDBG-funded activities are being carried out in a timely manner.

HUD will review the performance of each entitlement, HUD-administered small cities, and Insular Areas recipient to determine whether each recipient is carrying out its CDBG-assisted activities in a timely manner.
(a) Entitlement recipients and Non-entitlement CDBG grantees in Hawaii. (1) Before the funding of the next annual grant and absent contrary evidence satisfactory to HUD, HUD will consider an entitlement recipient or a non-entitlement CDBG grantee in Hawaii to be failing to carry out its CDBG activities in a timely manner if:
(i) Sixty days prior to the end of the grantee's current program year, the amount of entitlement grant funds available to the recipient under grant agreements but undisbursed by the U.S. Treasury is more than 1.5 times the entitlement grant amount for its current program year; and
(ii) The grantee fails to demonstrate to HUD's satisfaction that the lack of timeliness has resulted from factors beyond the grantee's reasonable control.
(2) Notwithstanding that the amount of funds in the line of credit indicates that the recipient is carrying out its activities in a timely manner pursuant to paragraph (a)(1) of this section, HUD may determine that the recipient is not carrying out its activities in a timely manner if:
(i) The amount of CDBG program income the recipient has on hand 60 days prior to the end of its current program year, together with the amount of funds in its CDBG line of credit, exceeds 1.5 times the entitlement grant amount for its current program year; and
(ii) The grantee fails to demonstrate to HUD's satisfaction that the lack of timeliness has resulted from factors beyond the grantee's reasonable control.
(3) In determining the appropriate corrective action to take with respect to a HUD determination that a recipient is not carrying out its activities in a timely manner pursuant to paragraphs (a)(1) or (a)(2) of this section, HUD will consider the likelihood that the recipient will expend a sufficient amount of funds over the next program year to reduce the amount of unexpended funds to a level that will fall within the standard described in paragraph (a)(1) of this section when HUD next measures the grantee's timeliness performance. For these purposes, HUD will take into account the extent to which funds on hand have been obligated by the recipient and its subrecipients for specific activities at the time the finding is made and other relevant information.
(b) HUD-administered Small Cities program in New York. The Department will, absent substantial evidence to the contrary, deem a HUD-administered Small Cities recipient in New York to be carrying out its CDBG-funded activities in a timely manner if the schedule for carrying out its activities, as contained in the approved application (including any subsequent amendment(s)), is being substantially met.
(c) Insular Areas recipients. (1) Before the funding of the next annual grant and absent contrary evidence satisfactory to HUD, HUD will consider an Insular Areas recipient to be failing to carry out its CDBG activities in a timely manner if:
(i) Sixty days prior to the end of the grantee's current program year, the amount of Insular Area grant funds available to the recipient under grant agreements but undisbursed by the U.S. Treasury is more than 2.0 times the Insular Area's grant amount for its current program year; and
(ii) The grantee fails to demonstrate to HUD's satisfaction that the lack of timeliness has resulted from factors beyond the grantee's reasonable control.
(2) Notwithstanding that the amount of funds in the line of credit indicates that the Insular Area recipient is carrying out its activities in a timely manner pursuant to paragraph (c)(1) of this section, HUD may determine that the recipient is not carrying out its activities in a timely manner if:
(i) The amount of CDBG program income the recipient has on hand 60 days prior to the end of its current program year, together with the amount of funds in its CDBG line of credit, exceeds 2.0 times the Insular Area's grant amount for its current program year; and
(ii) The grantee fails to demonstrate to HUD's satisfaction that the lack of timeliness has resulted from factors beyond the grantee's reasonable control.
(3) In determining the appropriate corrective action to take with respect to a HUD determination that a recipient is not carrying out its activities in a timely manner pursuant to paragraphs (c)(1) or (c)(2) of this section, HUD will consider the likelihood that the recipient will expend a sufficient amount of funds over the next program year to reduce the amount of unexpended funds to a level that will fall within the standards described in paragraphs (c)(1) and (2) of this section when HUD next measures the grantee's timeliness performance. For these purposes, HUD will take into account the extent to which funds on hand have been obligated by the recipient and its sub-recipients for specific activities at the time the finding is made and other relevant information.
(4) If a recipient is determined to be untimely pursuant to paragraphs (c)(1) or (c)(2) of this section in one year, and the recipient is again determined to be untimely in the following year, HUD may reduce the recipient's next grant by 100 percent of the amount in excess of twice the Insular Area's most recent CDBG grant, unless HUD determines that the untimeliness resulted from factors outside of the grantee's reasonable control.
(5) The first review under paragraphs (c)(1) and (c)(2) of this section will take place 60 days prior to the conclusion of the Fiscal Year 2006 program year.

Code of Federal Regulations

[53 FR 34466, Sept. 6, 1988, as amended at 60 FR 56917, Nov. 9, 1995; 72 FR 12536, Mar. 15, 2007; 72 FR 46371, Aug. 17, 2007]