242.16—Applications.

(a) Application process— (1) Market need. The approval process entails a determination of the market need of the proposal and stresses, on a market-wide basis, the impact of the proposed facility on, and its relationship to, other health care facilities and services (particularly other hospitals with mortgages insured under this part and hospitals that have a disproportionate share of Medicaid and uninsured patients or provide a substantial amount of charity care); the number and percentage of any excess beds; and demographic projections. Generally, Section 242 insurance may support start-up hospitals or major expansions of existing hospitals only if existing hospital capacity or services are clearly not adequate to meet the needs of the population in the service area.
(i) If the state has an official procedure for determining need for hospitals, HUD shall require that such procedure be followed before the application for insurance is submitted, and that the application document that need has also been established under that procedure.
(ii) The following factors are relevant in evaluating market need for the project and should be addressed, as applicable, in the study of market need and feasibility submitted with the application. Because each hospital presents a unique situation, there is no formula or cutoff level that applies to all applications:
(A) Service area definition;
(B) Existing or proposed hospital;
(C) Designation as sole community provider, Critical Access Hospital, or rural referral center;
(D) Community-wide use rates (discharges and days/1000);
(E) Statewide use rates (for benchmarking purposes);
(F) Current population and 5-year projection by age cohort;
(G) Staffed versus licensed beds;
(H) Applicant hospital's occupancy rate;
(I) Competitors' occupancy rates;
(J) Outpatient volume;
(K) Availability of emergency services;
(L) Teaching hospital status;
(M) Services offered by hospitals in the service area;
(N) Migration of patients out of the service area;
(O) Planned construction at other facilities in the region;
(P) Historical market share by major service category;
(Q) Disproportionate Share Hospital designation; and
(R) Distance to other hospitals.
(2) Operating margin and debt service coverage ratio. (i) Hospitals with an aggregate operating margin of less than 0.00 when calculated from the three most recent annual audited financial statements are not eligible for Section 242 insurance, unless HUD determines, based on the financial data in those statements, that the hospital has achieved a financial turnaround resulting in a positive operating margin in the most recent year, calculated using classifications of items as operating or non-operating in accordance with guidance that shall be provided in written directives by HUD. In any event, HUD shall not issue an insurance commitment for any hospital in a turnaround situation that has not achieved 2 consecutive years of positive operating margin immediately prior to issuance of the commitment.
(ii) Hospitals with an average debt service coverage ratio of less than 1.25 in the 3 most recent audited years are not eligible for Section 242 insurance, unless HUD determines, based on the audited financial data, that the hospital has achieved a financial turnaround resulting in a debt service coverage ratio of at least 1.40 in the most recent year. In cases of refinancing at a lower interest rate, HUD may authorize the use of the projected debt service requirement in lieu of the historical debt in calculating the debt service coverage ratios for each of the prior 3 years. In cases where HUD authorizes the use of the projected debt service requirement in lieu of the historical debt to determine the debt service coverage ratio, hospitals must have an average debt service coverage ratio of 1.40 or greater.
(3) Financial feasibility. The approval process entails a determination of the financial feasibility of the proposal, i.e., a determination that it is probable that the proposed mortgagor will be able to meet its debt service requirements during the period projected. It includes analysis of the reimbursement structure of the proposed hospital (including patient/payer mix); actions of competitors; and the probable projected impact on the proposed hospital of general health care system trends, such as the development of alternative health care delivery systems and new reimbursement methods. In addition to historical operating margin, determination of financial feasibility includes, but is not limited to, evaluation of the following factors, which the application must address and which HUD will review:
(i) Current and projected gains from operations and a manageable debt load using reasonable assumptions;
(ii) Current debt service coverage ratio of 1.25 or higher and projected debt service coverage ratio of 1.40 or higher;
(iii) Cushion in the balance sheet sufficient to demonstrate the ability to withstand short periods of net operating losses without jeopardizing financial viability;
(iv) Patient utilization forecasts (including average length of stay, case intensity, discharges, area-wide use rates) that are consistent with the hospital's historical trends, future service mix, market trends, population forecasts, and business climate;
(v) The hospital's demonstrated ability to position itself to compete in its marketplace;
(vi) Organizational affiliations or relationships that help optimize financial, clinical, and operational performance;
(vii) Management's demonstrated ability to operate effectively and efficiently, and to develop effective strategies for addressing problem areas;
(viii) Systems in place to monitor hospital operations, revenues, and costs accurately and in a timely manner;
(ix) A Board that is appropriately constituted and provides effective oversight;
(x) Required licensures and approvals; and
(xi) Favorable ratings from the Joint Commission on Accreditation of Healthcare Organizations or other organizations acceptable to HUD.
(4) Preliminary Review. A Preliminary Review is a general overview of the acceptability of a potential mortgagor performed at the request of a hospital, a financial consultant representing a hospital, or a lender, to identify any factors that would likely cause an application to be rejected, should an application be submitted.
(i) The purpose of the preliminary review is for HUD to identify any obvious factors that would cause an application to be rejected, before the potential mortgagor or mortgagee expends resources to prepare one. The hospital, financial consultant, or lender shall submit a preliminary information package to HUD that provides evidence of statutory eligibility, market need, financial strength, and such other documentation as HUD may require. The scope of the preliminary review does not include approval of any specific site in the community.
(ii) If HUD identifies factors that would cause an application to be rejected, HUD shall issue a Preliminary Review Letter notifying the potential applicant that an application for mortgage insurance would probably not be successful and providing the reasons for this decision. Also, no further request from the proposed applicant for a Preliminary Review shall be entertained for a period of one year from the date of HUD's notification. HUD may grant an exception to this one-year limitation if, during the year, there is a major change in the circumstances that caused HUD to determine that the project would be rejected. For example, if the sole reason for HUD's determination was the hospital's failure to meet the historical operating margin test, and a new audited annual financial statement contains results that would cause the hospital to meet the test, then the lender may request a new Preliminary Review within one year of HUD's notification.
(iii) If HUD does not identify any factors that would cause an application to be rejected, HUD shall issue a Preliminary Review Letter advising the potential applicant that there appears to be no bar to the applicant's proceeding to the next step in the application process, provided that if a complete application is not received by HUD within one year following the date of HUD's letter, another Preliminary Review may be required, at HUD's discretion, before the application process may proceed.
(iv) The Commissioner's determination in the preliminary review phase that no factors have been identified that would cause an application to be rejected shall in no way be construed as an indication that a subsequent application will be approved.
(5) Preapplication meeting. The next step in the application process is the preapplication meeting. At HUD's discretion, this meeting may be held at HUD Headquarters in Washington, DC, or at another site agreeable to HUD and the potential applicant. The preapplication meeting is an opportunity for the potential mortgagor to summarize the proposed project, for HUD to summarize the application process, and for issues that could affect the eligibility or underwriting of the project to be identified and discussed to the extent possible. Following the meeting, HUD may:
(i) Advise the potential applicant that there appears to be no bar to submitting an application for mortgage insurance; or
(ii) Identify issues that must be resolved before a full application should be submitted for processing.
(b) Application contents. The application for mortgage insurance shall include exhibits that follow such guidance as to content and format that HUD shall provide from time to time. The application shall include:
(1) A description of the proposed sources and uses of funds;
(2) A description of the mortgagor entity, its ownership structure, and its directors and managers;
(3) A description of the project, the business plan of the hospital, and how the project will further that plan;
(4) Historical audited financial statements and interim year-to-date financial results (for existing hospitals);
(5) A study of market need and financial feasibility, addressing the factors listed in paragraphs (a)(1)(ii), (a)(2), and (a)(3) of this section, with assumptions and financial forecast clearly presented, and prepared by a certified accounting firm acceptable to HUD;
(6) Architectural plans and specifications in sufficient detail to enable a reasonable estimate of cost;
(7) Evidence that the hospital will be located in a state or political subdivision of a state with reasonable minimum standards of licensure and methods of operation for hospitals and satisfactory assurance that such standards will be applied and enforced with respect to the hospital;
(8) If the state has an official procedure for determining need for hospitals, evidence that such procedure has been followed and that need has been established under that procedure;
(9) A Phase I environmental report; and
(10) Such other exhibits as HUD shall require based upon the facts pertaining to the particular case.
(c) Fee. An application fee of $1.50 per thousand dollars of the amount of the loan to be insured shall be paid to HUD at the time the application is submitted to HUD for approval.
(d) Filing of application. An application for insurance of a mortgage on a project shall be submitted on an approved FHA form by an approved mortgagee and by the sponsors of such project to the FHA Office of Insured Health Care Facilities.
(e) Complete application. Only technically complete applications will be processed. Partial applications cannot be processed. Upon determination that an application is complete, HUD shall issue a Completeness Letter to the applicant stating that the application is complete.
(f) Application review. Upon receipt of a complete application, HUD shall evaluate the application to determine if eligibility, market need, financial feasibility, and compliance with applicable regulations (including but not limited to federal environmental regulations, wage rate regulations, and health care regulations) have been demonstrated, and to evaluate any other factors, including but not limited to risk to the Insurance Fund, that should be considered in determining if the application for mortgage insurance should be approved. As a part of this review, HUD may solicit the advice of private consultants and expert staff in the Department of Health and Human Services and other federal agencies. Based on review of the complete application, HUD may request additional information from the applicant. The timeliness of the applicant's submission of the additional information may affect the approval or disapproval of the application. The Commissioner's decision shall be communicated in the form of a Commitment Letter or a Rejection Letter. HUD will not issue a Commitment Letter until HUD completes the environmental review under 24 CFR 242.79.