4.201—Contents of application.
An application for amendment of a license for a water power project must contain the following information in the form specified.
Before the Federal Energy Regulatory Commission
Application for Amendment of License
(1) [Name of applicant] applies to the Federal Energy Regulatory Commission for an amendment of license for the [name of project] water power project.
(2) The exact name, business address, and telephone number of the applicant are:
(3) The applicant is a [citizen of the United States, association of citizens of the United States, domestic corporation, municipality, or state, as appropriate, see 16 U.S.C. 796], licensee for the water power project, designated as Project No. ___ in the records of the Federal Energy Regulatory Commission, issued on the ______ day of _______, 19__.
(4) The amendments of license proposed and the reason(s) why the proposed changes are necessary, are: [Give a statement or description]
(5)(i) The statutory or regulatory requirements of the state(s) in which the project would be located that affect the project as proposed with respect to bed and banks and to the appropriation, diversion, and use of water for power purposes are: [provide citation and brief identification of the nature of each requirement.]
(ii) The steps which the applicant has taken or plans to take to comply with each of the laws cited above are: [provide brief description for each law.]
(b) Required exhibits for capacity related amendments.
Any application to amend a license for a hydropower project that involves additional capacity not previously authorized, and that would increase the actual or proposed total installed capacity of the project, would result in an increase in the maximum hydraulic capacity of the project of 15 percent or more, and would result in an increase in the installed name-plate capacity of 2 megawatts or more, must contain the following exhibits, or revisions or additions to any exhibits on file, commensurate with the scope of the licensed project:
(1)
For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of more than 5 MW—Exhibits A, B, C, D, E, F, and G under § 4.41 of this chapter ;
(2)
For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of 1.5 MW or less—Exhibits E, F, and G under § 4.61 of this chapter ;
(3)
For amendment of a license for a water power project that, at the time the application is filed, is not constructed and is proposed to have a total installed generating capacity of 5 MW or less, but more than 1.5 MW—Exhibits F and G under § 4.61 of this chapter, and Exhibit E under § 4.41 of this chapter ;
(4)
For amendment of a license for a water power project that, at the time the application for amendment is filed, has been constructed, and is proposed to have a total installed generating capacity of 5 MW or less—Exhibit E, F and G under § 4.61 of this chapter ;
(5)
For amendment of a license for a water power project that, at the time the application is filed, has been constructed and is proposed to have a total installed generating capacity of more than 5 MW—Exhibits A, B, C, D, E, F, and G under § 4.51 of this chapter.
(c) Required exhibits for non-capacity related amendments.
Any application to amend a license for a water power project that would not be a capacity related amendment as described in paragraph (b) of this section must contain those exhibits that require revision in light of the nature of the proposed amendments.
(d) Consultation and waiver.
(1)
If an applicant for license under this subpart believes that any exhibit required under paragraph (b) of this section is inappropriate with respect to the particular amendment of license sought by the applicant, a petition for waiver of the requirement to submit such exhibit may be submitted to the Commission under § 385.207(c)(4) of this chapter, after consultation with the Commission's Division by Hydropower Licensing.
(2)
A licensee wishing to file an application for amendment of license under this section may seek advice from the Commission staff regarding which exhibits(s) must be submitted and whether the proposed amendment is consistent with the scope of the existing licensed project.