4.101—Applicability.
This subpart provides procedures for exemption on a case-specific basis from all or part of Part I of the Federal Power Act (Act), including licensing, for small hydroelectric power projects as defined in § 4.30(b)(29).
Code of Federal Regulations
(Energy Security Act of 1980, Pub. L. 96-294, 94 Stat. 611; Federal Power Act, as amended (
16 U.S.C. 792-828c
); Public Utility Regulatory Policies Act of 1978 (
16 U.S.C. 2601-264
5); and the Department of Energy Organization Act (
42 U.S.C. 7101-735
2); E.O. 12009, 3 CFR 142 (1978))
Code of Federal Regulations
[Order 202, 47 FR 4243, Jan. 29, 1982, as amended by Order 413, 50 FR 11687, Mar. 25, 1985; Order 482, 52 FR 39630, Oct. 23, 1987; Order 2002, 68 FR 51121, Aug. 25, 2003]