35.13—Filing of changes in rate schedules, tariffs or service agreements.

Contents
(a) General rule.
(1) Filing for any rate schedule change not otherwise excepted.
(2) Abbreviated filing requirements.
(3) Cost of service data required by letter.
(b) General information.
(c) Information relating to the effect of the rate schedule change.
(d) Cost of service information.
(1) Filing of Period I data.
(2) Filing of Period II data.
(3) Definitions.
(4) Test period.
(5) Work papers.
(6) Additional information.
(7) Attestation.
(e) Testimony and exhibits.
(1) Filing requirements.
(2) Case in chief.
(3) Burden of proof.
(f) Filing by parties concurring in coordination and interchange arrangements.
(g) Commission precedents and policy.
(h) Cost of service statements.
(1) AA—Balance sheets.
(2) AB—Income statements.
(3) AC—Retained earnings statements.
(4) AD—Cost of plant.
(5) AE—Accumulated depreciation and amortization.
(6) AF—Specified deferred credits.
(7) AG—Specified plant accounts (other than plant in service) and deferred debits.
(8) AH—Operation and maintenance expenses.
(9) AI—Wages and salaries.
(10) AJ—Depreciation and amortization expenses.
(11) AK—Taxes other than income taxes.
(12) AL—Working capital.
(13) AM—Construction work in progress.
(14) AN—Notes payable.
(15) AO—Rate for allowance for funds used during construction.
(16) AP—Federal income tax deductions—interest.
(17) AQ—Federal income tax deductions—other than interest.
(18) AR—Federal tax adjustments.
(19) AS—Additional state income tax deductions.
(20) AT—State tax adjustments.
(21) AU—Revenue credits.
(22) AV—Rate of return.
(23) AW—Cost of short-term debt.
(24) AX—Other recent and pending rate changes.
(25) AY—Income and revenue tax rate data.
(26) BA—Wholesale customer rate groups.
(27) BB—Allocation demand and capability data.
(28) BC—Reliability data.
(29) BD—Allocation energy and supporting data.
(30) BE—Specific assignment data.
(31) BF—Exclusive-use commitments of major power supply facilities.
(32) BG—Revenue data to reflect changed rates.
(33) BH—Revenue data to reflect present rates.
(34) BI—Fuel cost adjustment factors.
(35) BJ—Summary data tables.
(36) BK—Electric utility department cost of service, total and as allocated.
(37) BL—Rate design information.
(38) Statement BM—Construction program statement.
(a) General rule. Every public utility shall file the information required by this section, as applicable, at the time it files with the Commission under § 35.1 all or part of a rate schedule, tariff or service agreement to supersede or otherwise change the provisions of a rate schedule, tariff or service agreement filed with the Commission under § 35.1. Any petition filed under § 385.207 of this chapter for waiver of any provision of this section shall specifically identify the requirement that the applicant wishes the Commission to waive.
(1) Filing for any rate schedule change or tariff not otherwise excepted. Except as provided in paragraph (a)(2) of this section, any utility that files a rate schedule, tariff, or service agreement change shall submit with its filing the information specified in paragraphs (b), (c), (d), (e), and (h) of this section, in accordance with paragraph (g) of this section.
(2) Abbreviated filing requirements— (i) For certain small rate increases. Any utility that files a rate increase for power or transmission services not covered by paragraph (a)(2)(ii) of this section may elect to file under this paragraph instead of paragraph (a)(1) of this section, if the proposed increase for the Test Period, as defined in paragraph (a)(2)(i)(A) of this section, is equal to or less than $200,000, regardless of customer consent, or equal to or less than $1 million if all wholesale customers that belong to the affected rate class consent.
(A) Definition: The Test Period, for purposes of paragraph (a)(2)(i) of this section, means the most recent calendar year for which actual data are available, the last day of which is no more than fifteen months before the date of tender for filing under § 35.1 of the notice of rate schedule.
(B) Any utility that elects to file under this subparagraph must file the following information, conforming its submission to any rule of general applicability and to any Commission order specifically applicable to such utility:
(1) A complete cost of service analysis for the Test Period, consistent with the requirements of paragraph (h)(36), Statement BK, of this section.
(2) A complete derivation and explanation of all allocation factors and special assignments, consistent with the information required in § 35.12(b)(5).
(3) A complete calculation of revenues for the Test Period and for the first 12 months after the proposed effective date, consistent with the requirements of paragraph (c)(1) of this section.
(4) If the proposed rates contain a fuel cost or purchased economic power adjustment clause, as defined in § 35.14, the company must provide the derivation of its base cost of fuel (Fb) and its monthly fuel factors (Fm) for the Test Period and the resulting fuel adjustment clause revenues. If any pro forma adjustments affect the fuel clause in any way, the company must show the impact on Fm, kWh sales in the base period (Sm), Fb and kWh sales in the current period (Sb), as well as on fuel adjustment clause revenues.
(5) Rate design calculations and narrative consistent with the information required in paragraph (h)(37) of this section and in § 35.12(b)(5).
(6) The information required in paragraphs (b), (c)(2) and (c)(3) of this section and in § 35.12(b)(2).
(C) Data shall be reconciled with the utility's most recent FERC Form 1. If the utility has not yet submitted Form 1 for the Test Period, the utility shall submit the relevant Form 1 pages in draft form.
(D) The utility may make pro forma adjustments for post-Test Period changes that occur before the proposed effective date and that are known and measurable at the time of filing. The utility shall provide a narrative statement explaining all pro forma adjustments.
(E) If the utility models its filing in whole or in part on retail rate decisions or settlements, the utility must provide detailed calculations and a narrative statement showing how all retail rate treatments are factored into the cost of service.
(F) If the Commission sets the filing for hearing, the Commission will allow the company a specific time period in which to file testimony, exhibits, and supplemental workpapers to complete its case-in-chief. While not required under this subpart, a utility may elect to submit Statements AA through BM for the Test Period in accord with the requirements of paragraphs (d), (g) and (h) of this section.
(ii) Rate increases for service of short duration or for interchange or coordination service. Any utility that files a rate increase for any service of short duration and of a type for which the need and usage cannot be reasonably forecasted (such as emergency or short-term power), or for service that is an integral part of a coordination and interchange arrangement, may submit with its filing only the information required in paragraphs (b), (c) and (h)(37) of this section and in § 35.12(b)(2) and (b)(5), conforming its submission to any rule of general applicability and to any Commission order specifically applicable to such utility.
(iii) For rate schedule, tariff, or service agreement changes other than rate increases. Any utility that files a rate change that does not provide for a rate increase or that provides for a rate increase that is based solely on a change in delivery points, a change in delivery voltage, or a similar change in service, must submit with its filing only the information required in paragraphs (b) and (c) of this section.
(iv) Computing rate increases. For purposes of this subparagraph and paragraph (d)(2)(ii) of this section, the amount of any rate increase shall be the difference between the total revenues to be recovered under the rate change and the total revenues recovered or recoverable under the rate to be superseded or supplemented and shall be determined by:
(A) applying the components of the rate to be superseded or supplemented to the billing determinants for the twelve months of Period I;
(B) Applying the components of the rate change to the billing determinants for the twelve months of Period I; and
(C) Subtracting the total revenues under subclause (A) from the total revenues under subclause (B).
(3) Cost of service data required by letter. The Director of the Office of Energy Market Regulation may, by letter, require a utility that is not required under paragraph (a)(1) of this section to submit cost of service data to submit such specified cost of service data as are needed for Commission analysis of the rate schedule change.
(b) General information. Any utility subject to paragraph (a) of this section shall file the following general information:
(1) A list of documents submitted with the rate change;
(2) The date on which the utility proposes to make the rate change effective;
(3) The names and addresses of persons to whom a copy of the rate change has been posted;
(4) A brief description of the rate change;
(5) A statement of the reasons for the rate change;
(6) A showing that all requisite agreement to the rate change, or to the filing of the rate change, including any agreement required by contract, has in fact been obtained;
(7) A statement showing any expenses or costs included in the cost of service statements for Period I or Period II, as defined in paragraph (d)(3) of this section, that have been alleged or judged in any administrative or judicial proceeding to be illegal, duplicative, or unnecessary costs that are demonstrably the product of discriminatory employment practices; and
(c) Information relating to the effect of the rate change. Any utility subject to paragraph (a) of this section shall also file the following information or materials:
(1) A table or statement comparing sales and services and revenues from sales and services under the rate schedule, tariff, or service agreement to be superseded and under the rate change, by applying the components of each such rate schedule or tariff to the billing determinants for each class of service, for each customer, and for each delivery point or set of delivery points that constitutes a billing unit:
(i) Except as provided in clause (ii), for each of the twelve months immediately before and each of the twelve months immediately after the proposed effective date of the rate change, and the total for each of the two twelve month periods; or
(ii) At the election of the utility:
(A) If the utility files Statements BG and BH under paragraph (h) for Period I, for each of the twelve months of Period I instead of for the twelve months immediately before the proposed effective date of the rate change; and
(B) If Period II is the test period, for each of the twelve months of Period II instead of for the twelve months immediately after the proposed effective date of the rate change;
(2) A comparison of the rate change and the utility's other rates for similar wholesale for resale and transmission services; and
(3) If any specifically assignable facilities have been or will be installed or modified in order to supply service under the ratechange, an appropriate map or sketch and single line diagram showing the additions or changes to be made.
(d) Cost of service information— (1) Filing of Period I data. Any utility that is required under paragraph (a)(1) of this section to submit cost of service information, or that is subject to the exceptions in paragraphs (a)(2)(i) and (a)(2)(ii) of this section but elects to file such information, shall submit Statements AA through BM under paragraph (h) of this section using:
(i) Unadjusted Period I data; or
(ii) Period I data adjusted to reflect changes that affect revenues and costs prior to the proposed effective date of the rate change and that are known and measurable with reasonable accuracy at the time the rate schedule change is filed, if such utility:
(A) Is not required to and does not file Period II data;
(B) Adjusts all Period I data to reflect such changes; and
(C) Fully supports the adjustments in the appropriate cost of service statements.
(2) Filing of Period II data. (i) Except as provided in clause (ii) of this subparagraph, any utility that is required under paragraph (a)(1) of this section to submit cost of service information shall submit Statements AA through BM described in paragraph (h) using estimated costs and revenues for Period II;
(ii) A utility may elect not to file Period II data if:
(A) The utility files a rate increase that is less than one million dollars for Period I; or
(B) All wholesale customers that belong to the affected rate class have consented to the rate increase.
(3) Definitions. For purposes of this section:
(i) Period I means the most recent twelve consecutive months, or the most recent calendar year, for which actual data are available, the last day of which is no more than fifteen months before the date of tender for filing under § 35.1 of the notice of rate change;
(ii) Period II means any period of twelve consecutive months after the end of Period I that begins:
(A) No earlier than nine months before the date on which the rate change is proposed to become effective; and
(B) No later than three months after the date on which the rate change is proposed to become effective.
(4) Test period. If Period II data are not submitted for Statements AA through BM, Period I shall be the test period. If Period II data are submitted for Statements AA through BM, Period II shall be the test period.
(5) Work papers. A utility that files adjusted Period I data or that files Period II data shall submit all work papers relating to such data. The utility shall provide a comprehensive explanation of the bases for the adjustments or estimates and, if such adjustments or estimates are based on a regularly prepared corporate budget, shall include relevant excerpts from such budget. Work papers and documents containing additional explanatory material shall be provided in electronic format, shall be legible, shall be assigned page numbers, and shall be marked, organized and indexed according to:
(A) Subject matter;
(B) The cost of service statements to which they apply; and
(C) Witness.
(6) Attestation. A utility shall include in its filing an attestation by its chief accounting officer or another of its officers that, to the best of that officer's knowledge, information, and belief, the cost of service statements and supporting data submitted under this paragraph are true, accurate, and current representations of the utility's books, budgets, or other corporate documents.
(e) Testimony and exhibits— (1) Filing requirements. A utility subject to paragraph (a)(1) of this section shall file Statements AA through BM under paragraph (h) as exhibits with its rate change and may file any other exhibits in support of its rate schedule change.
(ii) A utility subject to paragraph (a)(1) of this section shall file prepared testimony. Such testimony shall include an explanation of all exhibits, inlcuding Statements AA through BM, and shall include support for all adjustments to book or budgeted data relied on in preparing the exhibits.
(iii) To the extent that testimony and exhibits other than Statements AA through BM duplicate information required to be submitted in such statements, the testimony and exhibits may incorporate such information by referencing the specific statement containing such material.
(2) Case in chief. In order to avoid delay in processing rate filings, such cost of service statements, testimony, and other exhibits described in paragraph (e)(1) of this section shall be the utility's case in chief in the event the matter is set for hearing.
(3) Burden of proof. Any utility that files a rate increase shall be prepared to go forward at a hearing on reasonable notice on the data submitted under this section, to sustain the burden of proof under the Federal Power Act of establishing that the rate increase is just and reasonable and not unduly discriminatory or preferential or otherwise unlawful within the meaning of the Act.
(f) Filing by parties concurring in coordination and interchange arrangements. For coordination and interchange arrangements in the nature of power pooling transactions, all information required to be submitted in support of a rate change under paragraphs (a)(1), (2), and (3) of this section shall be submitted by each party filing a certificate of concurrence under § 35.1. If a representative is designated and authorized in accordance with § 35.1 to file supporting information on behalf of all parties to a rate change, such filing shall fulfill the requirement in this paragraph for individual submittals by each party.
(g) Commission precedents and policy. If a utility submits cost of service data under paragraph (d) of this section, it shall conform all such submissions to any rule of general applicability and to any Commission order specifically applicable to such utility.
(h) Cost of service statements. Any utility subject to paragraph (a)(1) of this section shall submit the following Statements AA through BM in accordance with the requirements of paragraphs (d) and (g) of this section.
(1) Statement AA—Balance sheets. Statement AA consists of balance sheets as of the beginning and the end of both Period I and Period II, and the most recently available balance sheet, including any applicable notes, and an explanation of any significant accounting changes since the most recent filing by the utility under this section that involves the same wholesale customer rate class. Balance sheets shall be constructed in accordance with the annual report form for electric utilities specified in part 141.
(2) Statement AB—Income statements. Statement AB consists of income statements for both Period I and Period II, and the most recently available income statement, including any applicable notes, and an explanation of any significant accounting changes since the most recent filing by the utility under this section that involves the same wholesale customer rate class. Income statements shall be prepared in accordance with the annual report form for electric utilities specified in part 141.
(3) Statement AC—Retained earnings statements. Statement AC consists of retained earnings statements for both Period I and Period II, and the most recently available retained earnings statement, including any notes applicable thereto. Retained earnings statements shall be prepared in accordance with the annual report form for electric utilities specified in part 141.
(4) Statement AD—Cost of plant. Statement AD is a statement of the original cost of total electric plant in service according to functional classification for Period I and Period II. If the plant functions and subfunctions for Period I and Period II are different, the utility shall explain and justify the differences.
(i) For each separately identified function and subfunction of production plant or transmission plant, the utility shall state the original cost as of the beginning of the first month and the end of each month of both Period I and Period II, with an average of the thirteen balances for each period. If any of the Period I or Period II thirteen monthly balances is not available or is unrepresentative of the current plan of the utility for plant in service, the utility shall provide an explanation of the relevant circumstances.
(ii) For each separately identified function and subfunction of plant other than production or transmission, the utility shall state the original cost as of the beginning and the end of both Period I and Period II, with an average of the beginning and end balances for each period. If any of the Period I or Period II balances is not available or is unrepresentative of the current plan of the utility for plant in service, the utility shall provide an explanation of the relevant circumstances.
(iii) The utility shall show the electric plant in service in accordance with each of the following five major functional classifications:
(A) Production;
(B) Transmission;
(C) Distribution;
(D) General and Intangible; and
(E) Common and Other.
(iv) To the extent feasible, the utility shall show completed construction not classified in accordance with clause (iii) in accordance with tentative classification to major functional accounts. If this is not feasible, the utility shall describe such facilities as other plant under clause (iii)(E).
(v) If a utility designs its rate change so that subdivision of the major functional classifications is necessary to support the changed rate, the utility shall supply the original cost information for any of the five major functional plant classifications in clause (iii) that are divided into subfunctional categories. If subfunctional original cost information is provided, the utility shall explain the importance of providing such information to support the changed rate. The utility shall describe each subfunctional category in substantive terms, such as steam electric production or high voltage transmission.
(vi) The utility shall select any subfunctional categories, as appropriate, under the following criteria:
(A) Production plant categories shall be established as necessary to segregate costs for production services with special characteristics, such as base, intermediate or peaking load. The utility shall provide a description of each such service and shall list a brief descriptive title for each corresponding subfunctional category.
(B) Transmission plant categories shall be chosen to reflect the extent to which the facilities are proposed to be allocated on a common basis among all or specific segments of utility services. For descriptive purposes, plant may also be categorized according to accounting or engineering terminology, such as high voltage overhead lines. The utility shall provide brief descriptive transmission category titles and explain the basis for the titles. If a utility allocates all transmission plant among utility services on the basis of a single set of allocation data, the utility may show original cost in total without subfunctionalization.
(C) Distribution plant categories shall be selected according to engineering or use characteristics meaningful for allocations or assignments to wholesale services such as substations, overhead lines, meters, or non-wholesale. The utility shall provide brief descriptive distribution category titles and shall explain the basis for the titles.
(D) If the utility divides any general, intangible, common, and other plant functional classifications into subfunctional categories, the subfunctional categories shall be chosen to group together facilities that share a common basis for allocation between wholesale and other electric services. The utility shall provide a brief descriptive title for each general and intangible subfunctional category, and for each common and other subfunctional category, with an explanation of the basis of each category selection. A utility need not divide the functional classifications of plant into subfunctional categories if these functions of plant are allocated in Statement BK on the basis of utility labor expenses.
(E) A separate category shall be provided for each specific assignment of plant reported in Statement BE. Such assignments are applicable principally but not necessarily exclusively to distribution facilities. The utility shall provide brief descriptive titles consistent with Statement BE.
(F) A separate category shall be provided for each exclusive-use commitment of major power supply facilities as required to be reported at Statement BF. The utility shall provide brief descriptive titles consistent with Statement BF.
(5) Statement AE—Accumulated depreciation and amortization. Statement AE is a statement of the accumulated provision for depreciation and amortization of electric plant for Period I and Period II, provided according to major functional classifications selected by the utility in Statement AD under paragraph (h)(4) and divided into the subfunctional categories selected by the utility in Statement AD, to the extent that subfunctionalized data are available.
(i) For each function and subfunction of electric production and transmission plant in service identified in Statement AD, the utility shall set forth the accumulated depreciation and amortization as of the beginning of the first month and the end of each month of both Period I and Period II. The utility shall state an average for each period computed as the average of the thirteen balances.
(ii) For each function and subfunction of electric plant in service other than production or transmission, identified in Statement AD, the utility shall state the accumulated depreciation and amortization as of the beginning and the end of Period I and Period II, with an average of the beginning and end balances for each period.
(iii) If any of the Period I or Period II balances is not available or is unrepresentative of the current plan of the utility for depreciation reserves, the utility shall provide an explanation of the relevant circumstances.
(iv) If accumulated depreciation and amortization data are not available for any subfunction selected in Statement AD, the utility shall:
(A) Provide a comparison of the current depreciation rate of the major functional classification and the depreciation rate estimated to be appropriate to the subfunctional category; and
(B) State and explain the estimation techniques which the utility proposes to utilize in the absence of subfunctional data, such as the proration of accumulated depreciation and amortization data among the subfunctional categories according to the data for electric plant in service in Statement AD. If any of the proposed estimation techniques require data that are not provided elsewhere in the cost of service statements in paragraph (h) of this section, the utility shall supply the necessary data in Statement AE.
(6) Statement AF—Specified deferred credits. Statement AF consists of balances of specified accounts and items which are to be considered in the determination of the net original cost rate base. All required balances are to be stated as of the beginning and end of both Period I and Period II, with an average of the beginning and end balances for each period. If any of the Period I and Period II balances is not available or is unrepresentative of the current operating plan of the utility, the utility shall include an explanation of the relevant circumstances. If subaccounts are maintained to reflect differences in ratemaking treatment among regulatory authorities that have jurisdiction, balances shall be provided in accordance with such subaccounts, with detailed explanations of the bases upon which the subaccounts were established and are maintained. The balances of deferred credits required to be filed in this statement are described in paragraph (h)(6) (i) through (v) of this section. All references to numbered accounts refer to the Commission's Uniform System of Accounts, 18 CFR part 101.
(i) The utility shall state total electric balances for accumulated deferred investment tax credits Account 255, and shall separate the credits into balances applicable to pre-1971 and post-1970 qualifying property additions. If the utility maintains records to show Account 255 component balances according to the major functional classifications identified in Statement AD under paragraph (h)(4), the utility shall provide the component balances by function. If the data are not available by function, the utility shall describe the procedure by which the utility believes it can reasonably estimate the portion of the total electric balances for each major functional classification. The utility may show by function the component balances obtained by applying the procedure. If such estimation requires data that are not provided elsewhere in the cost of service statements in this paragraph, the utility shall supply in Statement AF the necessary data, such as historical functional patterns of plant additions eligible for the tax credits. The utility shall state whether the Internal Revenue Code General Rule, § 46(f)(1), is applicable with respect to restrictions on credit treatment for ratemaking purposes. If the General Rule is not applicable, the utility shall state which election it has made with respect to special rules for ratable or immediate flow-through for ratemaking purposes.
(ii) The utility shall state the total electric component balances for accumulated deferred income tax Account 281 pertaining to accelerated amortization property. The utility shall show separate components for defense, pollution control, and other facilities. The utility shall show balances for each component and totaled for the electric utility department. If the utility maintains records to show Account 281 component balances according to the major functional classifications identified in Statement AD under paragraph (h)(4), the utility shall provide such component balances. If data are not available by function, the utility shall describe the procedure by which the utility believes it can reasonably estimate the portion of the total electric balances for each major functional classification. The utility may show by function the component balances obtained by applying the procedure. If such estimation requires data that are not provided elsewhere in the cost of service statements in this paragraph, the utility shall supply in Statement AF the necessary data.
(iii) The utility shall state the total electric component balances for accumulated deferred income tax Account 282 pertaining to electric utility property other than accelerated amortization property. The utility shall itemize the balances in Account 282, to the extent data are available, in detail sufficient to identify the specific major properties involved and shall list the balances according to the accounting entries, such as liberalized depreciation, for which interperiod tax allocation was used and included in this account. Component balances shall be shown individually and in total for the electric utility department. If the utility maintains records to show account 282 component balances according to the major functional classifications identified in Statement AD under paragraph (h)(4), the utility shall provide such component balances by function. If the data are not available by function, the utility shall describe the procedure by which the utility believes it can reasonably estimate the portion of the total electric balances for each major functional classification. The utility may show by function the component balances obtained by applying the procedure. If such estimation requires data that are not provided elsewhere in the cost of service statements in this paragraph, the utility shall supply in Statement AF the necessary data, such as historical functional patterns of plant additions.
(iv) The utility shall state the total electric component balances for accumulated deferred income tax Account 283 pertaining to interperiod income tax allocations not related to property. The utility shall itemize in detail balances in Account 283, to the extent data are available, and shall list the balances according to the accounting entries for which interperiod tax allocation was used and included in this account. Component balances shall be shown individually and in total for the electric utility department. If the utility maintains records to show Account 283 component balances according to the major functional classifications identified in Statement AD under paragraph (h)(4), the utility shall provide such component balances by function. If the data are not available by function, the utility shall describe the procedure by which the utility believes it can reasonably estimate the portion of the total electric balances for each major functional classification. The utility may show by function the component balances obtained by applying the procedure. If such estimation requires data that are not provided elsewhere in the cost of service statements in this paragraph, the filing shall supply in Statement AF the necessary data.
(v) The utility shall show electric utility balances for every other item that the utility believes should be included in Statement AF. The utility shall explain the reasons for inclusion of each item.
(7) Statement AG—Specified plant accounts (other than plant in service) and deferred debits. Statement AG is a statement of balances of specified accounts and items that are to be considered in the determination of the net original cost rate base. Except as prescribed in clause (ii), the utility shall state all required balances as of the beginning and the end of Period I and Period II, with an average of the beginning and end balances for each period. If any of the Period I or Period II balances is not available or is unrepresentative of the current operating plan of the utility, the utility shall provide a full explanation of the relevant circumstances. If subaccounts are maintained to reflect differences in ratemaking treatment among regulatory authorities having jurisdiction, the utility shall provide balances in accordance with such subaccounts, with detailed explanations of the bases upon which the subaccounts were established and are maintained. The balances required to be submitted under Statement AG are described in clauses (7)(i) through (vi).
(i) For each separately identified major functional classification selected by the utility in Statement AD, the utility shall state the electric utility land and land rights balances for electric plant held for future use in account 105. If itemized in detail, balances shall be totaled for each major functional classification.
(ii) The utility shall state the electric utility component balances in Accounts 107 and 120.1, individually and in total, for each item of construction work in progress for pollution control facilities, fuel conversion facilities, or any other facilities that qualify for inclusion in rate base under § 35.26. The utility shall state such balances for each major functional and subfunctional classification under Statement AD as of the beginning of the first month and the end of each month of Period I and Period II with an average of the 13 balances for each period.
(iii) For each major functional classification under Statement AD and with respect to property otherwise includable in plant in service, the utility shall state the balances for extraordinary property losses Account 182. If itemized in detail, balances shall be totaled for each major functional classification. The utility shall provide information about Commission authorization for any loss included in Account 182 and shall state when the loss was claimed for tax purposes.
(iv) The utility shall state the total electric component balances for accumulated deferred income taxes Account 190. The component balances in Account 190 shall be itemized in detail and listed according to the accounting entries for which interperiod tax allocation was used. Component balances shall be shown individually and in total for the electric utility department. If the utility maintains records to show Account 190 component balances according to the major functional classifications identified in Statement AD under paragraph (h)(4), the utility shall provide such component balances by function. If the data are not available by function, the filing utility shall describe the procedure by which the utility believes it can reasonably estimate the portion of the total electric balances for each major functional classification. The utility may show by function the component balances obtained by applying the procedure. If such estimation requires data that are not provided elsewhere in the cost of service statements in this paragraph, the utility shall supply in Statement AG the necessary data.
(v) Balances shall be shown for every other item that the utility believes should be included in Statement AG. The utility shall provide support for inclusion of each item, and a brief descriptive title for each such item.
(8) Statement AH— Operation and maintenance expenses. Statement AH is a statement of electric utility operation and maintenance expenses for Period I and Period II provided according to the accounts prescribed by the Commission's Uniform System of Accounts, 18 CFR part 101.
(i) For Period I and Period II, the utility shall itemize and subtotal all operation and maintenance expenses according to the major functional classifications of Statement AD in paragraph (h)(4) and the subfunctional categories of those classifications. The utility shall further divide the operation and maintenance expenses itemized under the production classification and each of its subfunctional categories to reflect expenses relating to the energy component (list each item by account number and compute fuel costs on an as-burned basis), the demand component, and any other production expenses.
(ii) For Period I and Period II, the utility shall report production operation and maintenance expenses according to appropriate account numbers. The utility shall apply the following principles in developing Period I and Period II production operation and maintenance data for this statement:
(A) Total production operation and maintenance expenses shall be segregated into energy, demand, and other components. The utility shall specifically state and support its criteria for classifications between energy and demand, and for use of the production other classification, such as specific assignments related to sales from particular generating units.
(B) Fuel expense for cost of service purposes shall be the total as-burned expense incurred. If the utility defers a portion of such expense for accounting purposes, the deferral amount shall be separately stated and accompanied by material that shows computational detail in support of such amount. If claimed nuclear fuel expense reflects a change in the estimated net salvage value of nuclear fuel, the utility shall show the amounts involved and explain the relevant circumstances.
(C) If the amount of production fuel expense is significantly affected by abnormal Period I water availability for hydroelectric generation, the utility shall explain how water availability was taken into account in developing projected Period II production fuel expenses.
(iii) For Period I and Period II, the utility shall report operation and maintenance expenses attributable to the transmission and distribution functions according to appropriate account numbers. If Period II transmission and distribution plant data are not provided by subfunctional category in Statement AD, the utility need only provide for Period II total operation and maintenance expenses for each function.
(iv) For Period I and Period II, the utility shall report in total for each period, operation and maintenance expenses incurred under each of the categories of customer accounting, customer service and information, and sales.
(v) For Period I and Period II, the utility shall itemize administrative and general expenses by groups that are directly assignable, such as regulatory Commission expenses, or that are related to selected plant or expense items for which an allocation to wholesale services is independently determinable, such as items related to labor expense or to a category of production plant in service. Administrative and general expenses shall include a detailed itemization of the general advertising Account 930.1 and the miscellaneous general expenses Account 930.2. If Account 930 data are not projected on a detailed basis for Period II, the utility shall provide its best estimate of the Account 930.1 expense items and a descriptive list of expense items anticipated as miscellaneous general expenses in Account 930.2. Where applicable, separate items shall be shown for general plant maintenance, and for common and other plant maintenance.
(vi) In addition to annual production data for Period I and Period II, the utility shall provide monthly expense data by accounts for fuel in Accounts 501, 518, and 547 and purchased power in Account 555. For each type of transaction, such as firm power or economy interchange power, monthly purchased power expense data shall be subtotaled separately for interchange receipts and deliveries. For monthly fuel Accounts 501, 518, and 547, and for each type of purchased power transaction, the monthly data shall identify components to be claimed under the fuel adjustment clause of the utility.
(9) Statement AI— Wages and salaries. Statement AI consists of statements of the electric utility wages and salaries, for Period I and Period II, that are included in operation and maintenance expenses reported in Statement AH.
(i) For Period I and Period II, the utility shall show the distribution of wages and salaries by function according to the form prescribed for operation and maintenance expenses by the Commission's Uniform System of Accounts, 18 CFR part 101. The statement shall also include by function additional wages and salaries attributable to common and other plant classifications identified in Statement AD in paragraph (h)(4).
(ii) For Period I and Period II, the utility shall show total production wages and salaries, itemized and subtotaled into energy and demand related components in accordance with classifications of Statement AH operation and maintenance production expenses of which production wages and salaries are a part.
(10) Statement AJ—Depreciation and amortization expenses. Statement AJ consists of statements of depreciation and amortization expenses for Period I and Period II.
(i) For Period I and Period II, the utility shall show the depreciation and amortization expenses and the depreciable plant balances of the filing utility, in accordance with major functional classifications selected by the utility in Statement AD under paragraph (h)(4).
(ii) The utility shall divide the major functional classifications of depreciation and amortization expenses shown in clause (i) into the subfunctional categories selected by the utility for electric plant in service in Statement AD, to the extent such data are available.
(iii) If depreciation and amortization expense data are not available for any subfunctional category selected in Statement AD, the utility shall:
(A) Provide a comparison of the current depreciation rate of