152.319—Monitoring and reporting of program performance.
(c) Airport development.
Unless otherwise requested by the Administrator, the sponsor of a project for airport development shall submit a performance report, on an annual basis, that must include—
(1)
A comparison of actual accomplishments to the goals established for the period, made, if applicable, on a quantitative basis related to cost data for computation of unit costs;
(3)
Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high unit cost.
(d) Airport planning.
The sponsor of a project for airport master planning or a planning agency conducting a project for airport system planning shall submit a performance report, on a quarterly basis, that must include:
(1)
A comparison of actual accomplishments to the goals established for the period, made, if applicable, on a quantitative basis related to costs for computation of work element costs;
(3)
Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high work element cost.